SHREE KURLAI COMPLEX

P99000032754 · NEAR KURLAI TEMPLE · promoter Shree Mangalmurti Associates

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP99000032754
Registered on24 Jan 2022
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Mangalmurti Associates is the promoter of record on 50 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 1 homes filed with MahaRERA, 0 are sold/booked and 1 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1001377 sqft (35.04 sqm)₹11.88 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 1 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SHREE KURLAI COMPLEX BUILDING NO 011G+6130 Jun 2025
SHREE KURLAI COMPLEX BUILDING NO 02 WING A AND B1G+6-30 Jun 2025
SHREE KURLAI COMPLEX BUILDING NO 03 WING A AND B1G+6-30 Jun 2025

Unit mix on the filing: 1 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at NEAR KURLAI TEMPLE, SAPHALE VILLAGE ROAD, Palghar, Palghar, 401102. Per the filed land record, the plot is bounded to the north by 158, to the south by 158, to the east by EXISTING VILLAGE ROAD and to the west by 158. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport68 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Makane

Galaxy Complex
possession by Jul 2026 · Ksquare Realty Private Limited
Balaji Heights
possession by Dec 2026 · Tirupati Enterprises
Excellence Residency 2
possession by Dec 2026 · SAI Excellence Realtors
Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra

Major developers building in Makane

Other RERA-registered projects in Palghar

Shree Lambodar Heights
declared completion Feb 2023 · Shree Sadguru Enterprises
Shree Mahalaxmi Traders
possession by Jul 2026 · Shree Mahalaxmi Traders
Shree Mahaveer Apartment Bldg. NO. - 1 - Type 2b/ B Wing
possession by Mar 2028 · Shree Mahaveer Developers
Shree Maruti Co-Op. Housing Society Ltd
declared completion Mar 2025 · Rameshwaram Enterprises
Shree Nath Nagar NO 1 AND 2
possession by Jul 2028 · Shreenath Enterprises
Shree Niwas 8
possession by Dec 2028 · Pravin Madhukar Raut

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026