Mumbai/Project record

MahaRERA · the public record

SHREE MANDAR CHSL

GANDHI NAGAR · V. V. ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700021387

Delivery and registration

When is the project declared for completion?

SHREE MANDAR CHSL is registered with MahaRERA as P51700021387 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700021387
Registered on24 Jun 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE MANDAR CHSL record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE MANDAR CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
SHREE MANDAR1G+631 Dec 2021

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for SHREE MANDAR CHSL, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019862817/10/2021V V ENTERPRISES vs MRS ANJALLEE PARESH CHHEDAorder passed
CC00600000019870417/10/2021V V Enterprises vs MRS ANJALLEE PARESH CHHEDAorder passed
CC1250456621/12/2025Shree Mandar CHSL (society) vs V. V. ENTERPRISESorder passed

A co-operative housing society is recorded as the complainant (Shree Mandar CHSL), and MahaRERA has passed an order.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
ReraCC0060000001987042021Pending
ReraCC0060000001986282021Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025a) Residential Project is not completed b) Due to the COVID-19 pandemic, the regular flow of work is hampered on account of the unavailability of labor on a regular basis c) Lack

Location, Land & Connectivity

Located at GANDHI NAGAR, GANDHINAGAR, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by MUNICIPAL ROAD, to the south by PLOT NO 52, to the east by PLOT NO 48 and to the west by PLOT NO 50. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel
Sumati Skyline
possession by Sep 2026 · Subhash Skyline Infra
Vinayak Prerana
possession by Sep 2026 · Nakshatra Group
Shanu Majestic
possession by Dec 2026 · Fortune Group Of Construction
Balaji Annex
possession by Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders

Major developers building in Dombivli East

Other RERA-registered projects in Thane

Shree Mangalmurti CO. OP. Hsg. Soc. LTD
possession by Mar 2027 · Bhumija Enterprises
Shree Maruti Heights
possession by Mar 2029 · Sunita Enterprises
Shree Mauli Prabha
declared completion Oct 2024 · Shree Prabha Construction
Shree Nalini C.h.s Limited
declared completion Dec 2025 · Shree Ashtavinayak Infra
Shree Nandkumar Mahadev Ashirwad
possession by Dec 2029 · Manish Nandkumar Patil
Shree Narayan Park A-1
declared completion Apr 2024 · Shree Narayan Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026