MahaRERA Property Intelligence · Raigarh

SHREE PANDHARI APARTMENT

P52000022908 · SECTOR - 25 · promoter Sachin Pandharinath Koli

Certificate SignedDue 16 Nov 2023

Delivery & Registration

MahaRERA registrationP52000022908
Registered on01 Nov 2019
Promoter-declared completion16 Nov 2023
Current statusCertificate Signed
Against todayabout 32 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sachin Pandharinath Koli is the promoter of record on 32 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
LATA PANDHARI APARTMENT1G+716 Nov 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
16 Nov 202216 Nov 2023WE ARE UNDER THE PROCESS OF GETTING THE OC SO JUST NEED ONE YEAR EXTENSION

Location, Land & Connectivity

Located at SECTOR - 25, PLOT NUMBER 316, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by PLOT NUMBER 315, to the south by PLOT NUMBER 317, to the east by 9M Wide Road and to the west by PLOT NUMBER 302. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Shree Pandurang Gore Complex
declared completion Aug 2022 · Jain Builders & Developers
Shree Park
possession by Dec 2031 · Shree Infra
Shree Parshwanath Residency
possession by Feb 2027 · Not Available
Shree Pooja
declared completion Dec 2019 · Mangalam Buildcon
Shree Prasad
possession by Dec 2027 · Shree Sai Enterprises
Shree Pratham
declared completion Oct 2025 · Shree Siddhivinayak Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026