Mumbai/Project record

MahaRERA · the public record

Shreedham Classic

Mumbai Suburban · Shreedham Construction Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012234

Delivery and registration

When is the project declared for completion?

Shreedham Classic is registered with MahaRERA as P51800012234 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012234
Registered on01 Sep 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shreedham Classic record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shreedham Construction is the promoter of record on 5 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shreedham Classic in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28.

BuildingWingsFloorsDeclared completion
Shreedham Classic1G+28-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Shreedham Classic, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019852506/10/2021MURLI MADHAVAN vs SHREEDHAM CONSTRUCTIONS PVT. LTD.order passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019The Project is fully complete. We have applied for Occupancy Certificate of Rehab Portion. We have also received Fire NOC for Wing B and expecting to receive the fire NOC for Wing

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by Kumud Nagar, to the south by ST John School, to the east by SV Road and to the west by New Siddhart Nagar. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport9 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district18 km
Nariman Point / Fort26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreedham Construction Private Limited is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shreedham Construction Private Limited project & its RERA track record →

Other flagged projects by Shreedham Construction Private Limited

Shreedham Construction Private Limited
Developer in insolvency (NCLT)Thane
Shreedham Construction Private Limited
Developer in insolvency (NCLT)Thane

Other RERA-registered projects in Goregaon West

Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers
Vallabh Krupa Chsl
possession by Oct 2026 · Gun Rajan Constructions
Siddharth Nagar Gulmohar CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Paschim Jagruti CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Swami Vivekanand Chsl
possession by Dec 2026 · Dhariwal Developers Private Limited

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Shreejee Mrugarchana CHS LTD
declared completion Jul 2025 · Shreejee Buildcon Homes LLP
Shreeji Amber
possession by Jun 2030 · Shreeji Construction
Shreeji Ananta
possession by May 2031 · K Mehta AND Company
Shreeji Aspire
declared completion Nov 2022 · Shreeji Construction
Shreeji Atlantis Wing B
possession by Dec 2027 · Shreeji Construction
Shreeji Bliss
possession by Jan 2028 · Shreeji Construction

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026