Mumbai/Project record

MahaRERA · the public record

SHREERAM COMPLEX

GUT NO 189 · ZINAL BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

37units filed as unsoldInventory · 19 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
171registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000049212

Delivery and registration

When is the project declared for completion?

SHREERAM COMPLEX is registered with MahaRERA as P99000049212 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000049212
Registered on03 Feb 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREERAM COMPLEX record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Zinal Builders is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SHREERAM COMPLEX, ₹9.66 Cr of a declared ₹11.89 Cr estimated project cost is reported as incurred, about 81.2%, as at the last certified filing with MahaRERA.

81.2%

₹9.66 Cr

of ₹11.89 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SHREERAM COMPLEX, 79 of 123 homes filed with MahaRERA are recorded as sold or booked, about 64%, and 44 remain available.

64%sold

79 of 123 homes

₹12.78 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹12.20 Cr (about 95%) is recorded as collected and ₹58.30 Lakh as receivable. The project registers 171 homes in total, while this sold/unsold inventory filing covers 123 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 79 registered agreements, the effective carpet rate is ₹5,595/sqft, with eight in ten falling between ₹5,115 and ₹6,228 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 48 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 86 homes carry one, and 37 of the 171 are recorded unsold. Since we started watching this ledger, 7 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
405324 sqftRs 5,595 a sq ft typical, over Rs 3,676 to Rs 7,15852 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SHREERAM COMPLEX, 23 of the 37 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 36 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 171 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BLDG NO 1 A WING1G+768-
BLDG NO 2 A AND B WING1G+557-
BLDG NO 3 A AND B WING1G+546-

Unit mix on the filing: 171 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at GUT NO 189, MAKANE ROAD, Vasai, Palghar, 401102. Per the filed land record, the plot is bounded to the north by OPEN PLOT, to the south by VINAY GARDEN, to the east by OPEN PLOT and to the west by OPEN PLOT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Lower Parel / Worli business district17 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)19 km
Andheri MIDC / SEEPZ20 km
Nariman Point / Fort22 km
Powai / Hiranandani business park23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Zinal Builders AND Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Zinal Builders AND Developers

Zinal Builders AND Developers
FlaggedPalghar

Other RERA-registered projects in Makane

Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra
Nine Star Prestige Building NO. 1
possession by Dec 2026 · Nine Home Creators
Nine Star Prestige Building NO. 2
possession by Dec 2026 · Nine Home Creators
Ninestar Crown Bldg NO 5 Emerald
possession by Dec 2026 · Nine Homemakers

Other RERA-registered projects in Palghar

Shreeram Complex Bldg No 12 A And B Wings Residential With Commercial
declared completion Jun 2026 · M/s. Sairam Realtors
Shreya Ocean Complex, Building No.1, Wing B
declared completion Dec 2020 · Ashishkumar Jagdish Singh
Shri Dajiba Heights
possession by Dec 2027 · Shrijee Krupa Developers
Shri Ganesh APT-1
declared completion Dec 2021 · ABO Infra
Shri Ganeshkripa
declared completion Dec 2025 · Kiran Enterprises
Shri Hari HAR Plaza
declared completion Dec 2017 · Shri Hari HAR Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026