Mumbai/Project record

MahaRERA · the public record

SHRI HARI HAR PLAZA

Palghar · SHRI HARI HAR DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2017declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000003776

Delivery and registration

When is the project declared for completion?

SHRI HARI HAR PLAZA is registered with MahaRERA as P99000003776 and the promoter has declared completion for 31 Dec 2017.

31 Dec 2017

declared completion

105months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000003776
Registered on06 Aug 2017
Promoter-declared completion31 Dec 2017
Current statusCertificate Signed
Against todayabout 105 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRI HARI HAR PLAZA record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRI HARI HAR PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
SHRI HARI HAR PLAZA1G+2-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vada, Palghar, 421321. Per the filed land record, the plot is bounded to the north by ROAD, to the south by PLOT NO 166, to the east by PLOT NO 173 and to the west by PLOT NO 173. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~50 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park50 km
Andheri MIDC / SEEPZ51 km
Chhatrapati Shivaji Int'l Airport55 km
Bandra Kurla Complex (BKC)57 km
Lower Parel / Worli business district66 km
Nariman Point / Fort73 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shri Krishna
possession by Dec 2027 · V K Hosuing
Shri Krishna Heights
declared completion Nov 2024 · HMK Builders
Shri Krishna Heritage
possession by Dec 2030 · SAI Vishwas Developers
Shri Mahalaxmi APT
declared completion Dec 2021 · ABO Infra
Shri Rajendra Srushti
declared completion Jun 2024 · Srushti Developers
Shri Ram Residency
possession by Jul 2028 · Shri Ram Builder & Developer's

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026