30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000026892

Delivery and registration

When is the project declared for completion?

SHRI RAJENDRA SRUSHTI is registered with MahaRERA as P99000026892 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000026892
Registered on03 Nov 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRI RAJENDRA SRUSHTI record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Srushti Developers is the promoter of record on 34 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

34projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRI RAJENDRA SRUSHTI in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHRI RAJENDRA SRUSHTI BUILDING NO - 11G+401 Dec 2020
SHRI RAJENDRA SRUSHTI BUILDING NO -21G+401 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PALGHAR, MAHIM ROAD, Vasai, Palghar, 401402. Per the filed land record, the plot is bounded to the north by 19 40 47 75 N 72 45 11 70 E, to the south by 19 40 46 51 N 72 45 11 71 E, to the east by 19 40 47 17 N 72 45 12 16 E and to the west by 19 40 47 11 N 72 45 11 14 E. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Srushti Developers is the promoter on 9 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Srushti Developers project & its RERA track record →

Other flagged projects by Srushti Developers

Srushti Developers
FlaggedPalghar

Other RERA-registered projects in Palghar

Sanmukh Sunshine
Not filing quarterly progress reports · possession by Oct 2026 · Sanmukh Realty LLP
Bafna Luxuria
possession by Dec 2026 · Shrushti Developers
Krishna Solitaire - 1
possession by Dec 2026 · Inspiration SG Infracon LLP
Krishna Solitaire - 2
possession by Dec 2026 · Inspiration SG Infracon LLP
Shakti Industrial Estate
Not filing quarterly progress reports · possession by Dec 2026 · Shakti Krupa Developers
Star Signature City-Star Emerald
possession by Dec 2026 · Star Builders & Developers

Other RERA-registered projects in Palghar

Shri Ram Residency
possession by Jul 2028 · Shri Ram Builder & Developer's
Shri Saikripa
declared completion Dec 2025 · Kiran Enterprises
Shri Swami Samarth
declared completion Dec 2025 · Sandeep Bhaurao Landge
Shri Swami Samarth Apartment
possession by Dec 2028 · Surendra Singh
Shrihari Darshan
declared completion May 2026 · Mangalmurti Developers
Shrikrishna Heritage B AND C Wing
declared completion Dec 2023 · Shrikrishna Ventures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026