MahaRERA Property Intelligence · Palghar

SHRIKRISHNA HERITAGE B AND C WING

P99000022410 · Mahim · promoter Shrikrishna Ventures

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP99000022410
Registered on20 Sep 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shrikrishna Ventures is the promoter of record on 31 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Type-B Wing B and C1G+431 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mahim, Mahim Road, Palghar, Palghar, 401403. Per the filed land record, the plot is bounded to the north by SN 413-1, to the south by 412, to the east by SN 413-3-2 and to the west by SN 413-2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shrikrishna Ventures is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shrikrishna Ventures

Shrikrishna Ventures
FlaggedPalghar

Other RERA-registered projects in Manor

15 Manor - Belvedere 2
possession by Dec 2026 · RV Infra
Myzo Suites
possession by Dec 2027 · Myzo Infra Private Limited
Myzo Suites Building NO 3 - A Wing
Not filing quarterly progress reports · possession by Dec 2027 · Ayush Reality
Godrej Country Estate
declared completion Apr 2026 · Godrej Projects Development Limited
Bandhan Heritage Phase II
Not filing quarterly progress reports · declared completion Dec 2025 · Mahi Links
Riddhi Siddhi Park Phase-2
Past its declared completion date · declared completion Jun 2024 · Riddhi Siddhi Builders

Other RERA-registered projects in Palghar

Shrinathji Heights
declared completion Dec 2019 · Shrinathji Builder AND Developers
Shripal Crown Chsl
possession by Dec 2028 · Unnati Constructions
Shripal ONE
declared completion Feb 2025 · Shripal Homes LLP
Shripal Sattva - Bldg. 1
possession by Dec 2027 · Shripal Sattva LLP
Shripal Sattva Bldg. 2
possession by Dec 2028 · Shripal Sattva LLP
Shripal Shanti Phase - 1
declared completion Mar 2025 · Shripal Shanti LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026