Mumbai/Project record

MahaRERA · the public record

SHRI KRISHNA HEIGHTS

PLOT NO. A BUILDING 2 · HMK BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Nov 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Nov 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000030313

Delivery and registration

When is the project declared for completion?

SHRI KRISHNA HEIGHTS is registered with MahaRERA as P99000030313 and the promoter has declared completion for 01 Nov 2024.

01 Nov 2024

declared completion

22months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000030313
Registered on15 Aug 2021
Promoter-declared completion01 Nov 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRI KRISHNA HEIGHTS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRI KRISHNA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
SHRI KRISHNA HEIGHTS1G+1930 Nov 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered01 Nov 2024Due to Some hike in material prices and shortage of labour we could not complete the project within a prescribe date . hence we request you to kindly grant us 1 year extention

Location, Land & Connectivity

Located at PLOT NO. A BUILDING 2, A WING, Vasai, Palghar, 401208. Per the filed land record, the plot is bounded to the north by 6MTR WIDE INTERNAL ROAD, to the south by COMPOUND WALL, to the east by COMPOUND WALL and to the west by BUILDING NO 1. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~25 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ25 km
Powai / Hiranandani business park27 km
Chhatrapati Shivaji Int'l Airport30 km
Bandra Kurla Complex (BKC)32 km
Lower Parel / Worli business district40 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vasai East

AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP
Matoshri Heights
possession by Oct 2026 · Nagesh Hemant Patil
Hayaat Galaxy II
possession by Nov 2026 · M M Enterprises
Apeksha Complex
possession by Dec 2026 · Kothari Construction CO

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Shri Krishna Heritage
possession by Dec 2030 · SAI Vishwas Developers
Shri Mahalaxmi APT
declared completion Dec 2021 · ABO Infra
Shri Rajendra Srushti
declared completion Jun 2024 · Srushti Developers
Shri Ram Residency
possession by Jul 2028 · Shri Ram Builder & Developer's
Shri Saikripa
declared completion Dec 2025 · Kiran Enterprises
Shri Swami Samarth
declared completion Dec 2025 · Sandeep Bhaurao Landge

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026