Mumbai/Project record

MahaRERA · the public record

KALPATARU AVENUE

Palghar · SHRINATH REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000008892

Delivery and registration

When is the project declared for completion?

KALPATARU AVENUE is registered with MahaRERA as P99000008892 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000008892
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for KALPATARU AVENUE record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shrinath Realtors is the promoter of record on 22 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

22projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for KALPATARU AVENUE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
WINGS C, D, E1G+430 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2023Due to bullet train passing some part of land acuired by bullet train project we have received the new COMMENCEMENT CERTIFICATE On (17/05/2022).therefore we request you to to grant
30 Jun 202331 Dec 2023DUE TO BULLET TRAIN PASSING SOME PART OF LAND ACQUIRED BY BULLET TRAIN PROJECT.WE HAVE BY ATTACHED THE COPY OF NEW COMMENCEMENT CERTIFICATE AND LAYOUT WITH OUR APPLICATION.WE HERE
31 Dec 202331 Dec 2024DUE TO BULLET TRAIN PROJECT PASSING SOME PART OF OUR LAND ACQUIRED BY BULLET TRAIN PROJECT THEREFORE WE HAVE NOT RECEIVED OC FOR PUR PROJECT KALPATARU AVENUE BUT WE HAVE COMPLETED

Location, Land & Connectivity

Located at Vasai, Palghar, 401208. Per the filed land record, the plot is bounded to the north by 20 MTS WIDE DP ROAD S NO 8 9, to the south by S NO 15, to the east by CHANDIKA TEMPLE S NO 206 and to the west by S NO 22 23 24 25. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ27 km
Powai / Hiranandani business park29 km
Chhatrapati Shivaji Int'l Airport31 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort50 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shrinath Realtors is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Vasai East

AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP
Matoshri Heights
possession by Oct 2026 · Nagesh Hemant Patil
Hayaat Galaxy II
possession by Nov 2026 · M M Enterprises
Apeksha Complex
possession by Dec 2026 · Kothari Construction CO

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Kalpatru Avenue
possession by Dec 2030 · Crowngoldinfra LLP
Kamala Darshan
possession by Dec 2026 · Akshat Realty
Kamat Park
declared completion Apr 2019 · SAI Krishna Developers
Kamat Park II
possession by Dec 2028 · SAI Krishna Developers
Kanchan Avenue AND Kanchan Ratna
possession by Dec 2029 · Novel Estate
Kanchan Business Center
declared completion Jun 2024 · Novel Buildcon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026