Mumbai/Project record

MahaRERA · the public record

SHRI SHIVANAND CHS

BHASKAR COLONY · Trimity Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

19 Aug 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

19 Aug 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700024183

Delivery and registration

When is the project declared for completion?

SHRI SHIVANAND CHS is registered with MahaRERA as P51700024183 and the promoter has declared completion for 19 Aug 2024.

19 Aug 2024

declared completion

25months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700024183
Registered on24 Jan 2020
Promoter-declared completion19 Aug 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRI SHIVANAND CHS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Trimity Constructions is the promoter of record on 6 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRI SHIVANAND CHS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SBI Employees Shri Shivanand CHS Ltd1G+8-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SHRI SHIVANAND CHS, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020939313/12/2021STATE BANK OF INDIA EMPLOYEES, SHRI SHIVANAND CHS (society) vs TRIMITY CONSTRUCTIONSorder passed

A co-operative housing society is recorded as the complainant (STATE BANK OF INDIA EMPLOYEES, SHRI SHIVANAND CHS), and MahaRERA has passed an order.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2024As per the attachment
29 Jun 202419 Aug 2024As per attachment

Location, Land & Connectivity

Located at BHASKAR COLONY, GAVAND PATH, Thane, Thane, 400602. Per the filed land record, the plot is bounded to the north by RESERVE BANK OF INDIA CHSL, to the south by PUBLIC ROAD, to the east by PUBLIC ROAD and to the west by PUBLIC ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~154 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park154 km
Andheri MIDC / SEEPZ155 km
Chhatrapati Shivaji Int'l Airport159 km
Bandra Kurla Complex (BKC)161 km
Lower Parel / Worli business district169 km
Nariman Point / Fort176 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Trimity Constructions is the promoter on 4 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Trimity Constructions

Trimity Constructions
FlaggedThane
Trimity Constructions
FlaggedThane

Other RERA-registered projects in Naupada

Ashtavinayak Residency
possession by Sep 2026 · Ashvattha Realty LLP
Shree Krupa CO OP Housing Society
possession by Sep 2026 · Sharda Vastu Nirmitee Pvt. Ltd.
Ashirwad Co-Operative Housing Society Ltd
possession by Oct 2026 · Padmanabh Developers
Platinum Square
possession by Oct 2026 · Ratnamani Buildcon
Om Yashodhan Chsl
possession by Nov 2026 · Silver Stone Realty
Larkins 315 FIO-A
possession by Dec 2026 · M/S Pushpak Developers

Major developers building in Naupada

Other RERA-registered projects in Thane

Shri Shivsiddhi
possession by Dec 2028 · Shapes Realtors
Shri Varaladevi Residency
declared completion Jun 2025 · Mohan Mallesham Machha
Shri Venkatesh Krupa
declared completion Dec 2023 · Modi Developers
Shrihari Chandan Apartment
possession by Mar 2028 · Abhishek Shelters Limited
Shrikrishna Residency Cooperative Housing Society Limited
possession by Nov 2028 · Aaryaraj Developers LLP
Shrinath CO-Operative Housing Society LTD
declared completion Dec 2024 · Vidhi Buildcon Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026