MahaRERA Property Intelligence · Raigarh

SHUBH LAXMI APPARTMENT BLD A PHASE 1

P52000027605 · NAGOTHANE · promoter Shree Rajendra Developers

Certificate SignedDue 27 Sep 2025

Delivery & Registration

MahaRERA registrationP52000027605
Registered on23 Dec 2020
Promoter-declared completion27 Sep 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Rajendra Developers is the promoter of record on 161 projects, of which 21 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHUBH LAXMI APPARTMENT BLD A1G+431 Mar 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202427 Sep 2025sir because of less booking and financial crunches we could not complete the project however we are confident that we shall complete the project in extended period

Location, Land & Connectivity

Located at NAGOTHANE, NAGOTHANE, Roha, Raigarh, 402106. Per the filed land record, the plot is bounded to the north by S NO 34, to the south by 9 MTR INTERNAL ROAD, to the east by S NO 38 and to the west by MUMBAI GOA HIGHWAY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~61 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort55 km
Lower Parel / Worli business district61 km
Bandra Kurla Complex (BKC)66 km
Chhatrapati Shivaji Int'l Airport68 km
Powai / Hiranandani business park69 km
Andheri MIDC / SEEPZ72 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shree Rajendra Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Shree Rajendra Developers

Shree Rajendra Developers
FlaggedRaigarh

Other RERA-registered projects in Nagothane

Bhide Residency
possession by Dec 2026 · Gopikrishna Constrcution
MAN Saroj Plaza
possession by Jun 2027 · Not Available
Morya Home Town
possession by Dec 2027 · Morya Infraconstruct Private Limited
OM Sneh Prabha Complex
possession by Dec 2027 · Sanjay Ramchandra Dalavi
Zuha Park
possession by Dec 2027 · Jaleel Ahmad Patel
Amba Residency
possession by Dec 2028 · N R Builders And Developers

Other RERA-registered projects in Raigarh

Shubh Residence
declared completion Oct 2022 · Shalom Developers
Shubha
declared completion Dec 2017 · Envision Infra
Shubha
declared completion Dec 2018 · Parag Pankaj Thakker
Shubhada Coop Housing Societyproposed
declared completion Dec 2025 · Kaustubh Jeevan Kulkarni
Shubham Apartment
declared completion Dec 2019 · Ramesh Gulab Tupe
Shubham Complex 1B
declared completion Dec 2022 · Rekha Buildcon LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026