Mumbai/Project record

MahaRERA · the public record

Shubha

Mumbai Suburban · Parag Pankaj Thakker

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000003308

Delivery and registration

When is the project declared for completion?

Shubha is registered with MahaRERA as P52000003308 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000003308
Registered on05 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shubha record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Parag Pankaj Thakker is the promoter of record on 15 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

15projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shubha in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Shubha1G+4-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Shubha, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000005666521/10/2018RAMESH K MAHARAO vs SHREE MAHALAXMI DEVELOPERSorder passed
CC00600000008953026/06/2019ajaj patel vs parag thakkerorder passed

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by Survey No 18 Plot No 20, to the south by Survey No 85 Plot No 50, to the east by Survey No 85 Plot No 28 and to the west by Survey No 85 Plot No 18. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~48 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park48 km
Bandra Kurla Complex (BKC)51 km
Chhatrapati Shivaji Int'l Airport51 km
Andheri MIDC / SEEPZ52 km
Lower Parel / Worli business district55 km
Nariman Point / Fort57 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Parag Pankaj Thakker is the promoter on 10 MahaRERA-registered projects, of which 10 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Parag Pankaj Thakker project & its RERA track record →

Other flagged projects by Parag Pankaj Thakker

Parag Pankaj Thakker
Past its declared completion dateRaigarh
Parag Pankaj Thakker
Past its declared completion dateRaigarh
Parag Pankaj Thakker
Past its declared completion dateRaigarh
Parag Pankaj Thakker
Past its declared completion dateRaigarh
Parag Pankaj Thakker
Past its declared completion dateRaigarh
Parag Pankaj Thakker
Past its declared completion dateRaigarh

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

Shubhada Coop Housing Societyproposed
declared completion Dec 2025 · Kaustubh Jeevan Kulkarni
Shubham Complex 1B
declared completion Dec 2022 · Rekha Buildcon LLP
Shubham Ekadanta
possession by Dec 2026 · Darshan Pralhad Shinde
Shubham Gunina
possession by Dec 2027 · Shubham Gunina Infra
Shubham Residency
possession by Oct 2026 · G D Jain Infra Projects
Shubharambh Paradise
declared completion May 2026 · M/s Shubharambh Realty

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026