MahaRERA Property Intelligence · Mumbai Suburban

SHUBHAM

P51800010791 · promoter Aditya Associates

Certificate SignedDue 30 Nov 2021

Delivery & Registration

MahaRERA registrationP51800010791
Registered on31 Aug 2017
Promoter-declared completion30 Nov 2021
Current statusCertificate Signed
Against todayabout 56 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
TILAK NAGAR SHUBHAM CHSL1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Nov 202131 May 202110% work is pending and also noc is pending from other work

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by BUILDING NO 65, to the south by SCHOOL, to the east by BUILDING NO 67 and to the west by PG. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district11 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditya Associates is the promoter on 14 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Aditya Associates project & its RERA track record →

Other flagged projects by Aditya Associates

Aditya Associates
Past its declared completion dateMumbai Suburban
Aditya Associates
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Chembur

Silicon Hofe B Wing
possession by Jul 2026 · Shilpriya Builders AND Developers
Basil Residency
possession by Dec 2026 · Poseidon Realtors
Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
The Gateway
possession by Dec 2026 · Atmosphere Realty Pvt Ltd

Other RERA-registered projects in Mumbai Suburban

Shubham Alaska
declared completion Jun 2025 · Dipal Laxmichand Shah
Shubham Artesia
possession by Dec 2027 · Avvad Realtty LLP
Shubham Athena
declared completion Jun 2026 · Avvad Realcon LLP
Shubham Atlanta
declared completion Jun 2026 · Avvad Housing LLP
Shubham Atlantis
declared completion Dec 2024 · Avvad Realtty LLP
Shubham Atria
declared completion Dec 2022 · Dipal Laxmichand Shah

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026