275units filed as unsoldInventory · 20 September 2026
30 Jun 2030declared completionMahaRERA registration · read 02 Jul 2026
783registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1180002502390

Delivery and registration

When is the project declared for completion?

Sky City Tower H is registered with MahaRERA as PR1180002502390 and the promoter has declared completion for 30 Jun 2030.

30 Jun 2030

declared completion

45months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1180002502390
Registered on17 Feb 2026
Promoter-declared completion30 Jun 2030
Current statusCertificate Signed
Against today45 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sky City Tower H record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 02 Jul 2026

  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Incline Realty is the promoter of record on 9 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Construction

How much construction cost has been reported?

In Sky City Tower H, ₹183.05 Cr of a declared ₹603.70 Cr estimated project cost is reported as incurred, about 30.3%, as at the last certified filing with MahaRERA.

30.3%

₹183.05 Cr

of ₹603.70 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 02 Jul 2026

Sales

How much has actually been sold?

In Sky City Tower H, 36 of 311 homes filed with MahaRERA are recorded as sold or booked (30 with registered agreements and 6 booked), about 12%, and 275 remain available.

12%sold

36 of 311 homes

₹191.03 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹69.89 Cr (about 37%) is recorded as collected and ₹121.14 Cr as receivable. The project registers 783 homes in total, while this sold/unsold inventory filing covers 311 of them.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

What buyers actually paid: across 36 registered agreements, the effective carpet rate is ₹44,976/sqft, with eight in ten falling between ₹38,636 and ₹56,865 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 472 reserved.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 36 homes carry one, and 275 of the 783 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
24071,417 sqftRs 6.0695 cr typical, over Rs 5.3197 cr to Rs 6.6394 cr20 filed on this stack, floors 8–35

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Sky City Tower H, 134 of the 275 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 274 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+68 and 783 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RESI BLDG. NO. 2 Tower-'H'1G+68783-

Unit mix on the filing: 783 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Causes Court842007Ongoing
City Civil Court17942024Ongoing
Bombay High Court39452022Ongoing
Bombay High Court23892022Ongoing

Location, Land & Connectivity

Located at Borivali East, 36.60m wide Dattapada Road, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by CTS No. 107/E (pt) of Village Magathane, to the south by CTS No. 107/E (pt) of Village Magathane, to the east by CTS No. 107/E (pt) of Village Magathane and to the west by CTS No. 107/E (pt) of Village Magathane. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Incline Realty Private Limited is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Incline Realty Private Limited

Incline Realty Private Limited
FlaggedMumbai Suburban
Incline Realty Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Sky Crest
declared completion Mar 2026 · Sky Property Developers Private Limited
Sky Estella
possession by Mar 2027 · V K Developers
Sky Heights
possession by Dec 2028 · Skyline Developers
Sky Heights C-D
possession by Jun 2028 · R S Estate Developers Pvt Ltd
SKY Heights Phase II Wing D AND E
declared completion Dec 2023 · Crystal Constructions
SKY Lark
possession by Dec 2027 · Rajendra Pundlikrao Godshalwar

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.