MahaRERA Property Intelligence · Mumbai Suburban

SKY HEIGHTS PHASE II WING D AND E

P51800014393 · Dahisar · promoter Crystal Constructions

Certificate SignedDue 29 Dec 2023

Delivery & Registration

MahaRERA registrationP51800014393
Registered on29 Nov 2017
Promoter-declared completion29 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Crystal Constructions is the promoter of record on 60 projects, of which 8 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25.

BuildingWingsFloorsDeclared completion
SKY HEIGHTS PHASE II WING D AND E1G+2530 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202229 Dec 2023THE PROMOTER HAS ALREADY APPLIED FOR OC ON 27/09/2022 AND THE SAME IS BEING AWAITED COPY OF WHICH IS ATTACHED AS UNDER IN SR NO 2

Location, Land & Connectivity

Located at Dahisar, Suhasani Pawaskar Marg, Andheri, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by CTS NO 2947, to the south by SUHASINI PAWASKAR ROAD, to the east by 18-30 DP ROAD and to the west by CTS NO 2943 AND 2944. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ14 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Crystal Constructions is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Crystal Constructions

Crystal Constructions
FlaggedMumbai Suburban
Crystal Constructions
FlaggedMumbai Suburban

Other RERA-registered projects in Dahisar East

Sahakar Vista
possession by Jul 2026 · Sahakar Creation
Commercial Wing - NL Plaza And Residential Wing - NL Krishna
possession by Aug 2026 · Beautiful Properties Private Limited
Krishna Kripa
possession by Aug 2026 · Skyla Developers LLP
RAJ Capital
possession by Aug 2026 · RAJ Insignia Private Limited
Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

SKY Imperia
declared completion Dec 2025 · Skyline Star Constructions LLP
SKY Lark
possession by Dec 2027 · Rajendra Pundlikrao Godshalwar
Sky Residency Loksadan CHS Phase 1 Up To G Plus 7pt
declared completion Dec 2017 · Sky Property Developers Private Limited
SKY Sixty
possession by Dec 2028 · Skyline Harmony Constructions LLP
SKY Tower
declared completion Dec 2023 · Rajyog Realtors
Sky Villa
declared completion Dec 2020 · Ajanta Karmvir Constructions LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026