SOPHIA APARTMENT

P51700011312 · promoter Aaria Enterprises

Certificate SignedDue 15 Aug 2022

Delivery & Registration

MahaRERA registrationP51700011312
Registered on31 Aug 2017
Promoter-declared completion15 Aug 2022
Current statusCertificate Signed
Against todayabout 47 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aaria Enterprises is the promoter of record on 3 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SOPHIA APARTMENT1G+5-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by 12 MTR DP ROAD, to the south by PLOT NO 9 SURVEY NO 166P, to the east by 6 MTR INTERNAL ROAD and to the west by SURVEY NO 167. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park31 km
Andheri MIDC / SEEPZ34 km
Chhatrapati Shivaji Int'l Airport36 km
Bandra Kurla Complex (BKC)37 km
Lower Parel / Worli business district44 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

Space Residence - II Building NO. 4 A
possession by Dec 2027 · Space Realty
Space Residence - II - Building NO. 4 B
possession by Jan 2027 · Space Realty
Span Exotica
declared completion May 2018 · Infinity Creators
Span Exotica-Wing B
declared completion Mar 2019 · Siddhivinayak Developers
Span Signature
declared completion Dec 2024 · Annapurna Buildcon Infra PVT LTD
Span Trident Wing B
possession by Dec 2027 · Span Venture

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026