MahaRERA Property Intelligence · Palghar

SUDHA

P99000022954 · TEMBHODE · promoter Samarth Realty

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP99000022954
Registered on05 Nov 2019
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
SUDHA1G+1330 Dec 2021

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250097120/03/2025Vilas Uttam Gharat vs SAMARTH REALTYorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202231 Jul 2023.
30 Dec 202231 Dec 2023.

Location, Land & Connectivity

Located at TEMBHODE, TEMBHODE ROAD, Palghar, Palghar, 401404. Per the filed land record, the plot is bounded to the north by SERVEY NO 6, to the south by ROAD AND SERVEY NO 115, to the east by SERVEY NO 107 and to the west by SERVEY NO 115. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~65 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ65 km
Powai / Hiranandani business park67 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Shree SAI Apartment
possession by Jul 2026 · Shree SAI Jivdani Developers
Madhav Vatika - VI
possession by Jul 2026 · R M N H Developers LLP
Prithvi Anand Kuber Complex
possession by Jul 2026 · Prithvi Anand Housing And Land Developer
Vardhaman Divine
possession by Jul 2026 · Vardhaman AND Shah Associates
Symphony Heights
possession by Aug 2026 · Kreate Space LLP
Shree Puram - 2, Building No. 1
possession by Aug 2026 · Vastu Realities

Major developers building in Palghar

Other RERA-registered projects in Palghar

Sugandhi Square
possession by Dec 2026 · R. N. Realty
Sugandhi Vihar
declared completion Dec 2024 · Varsha Prakash Naik
Sugandhi Vihar Phase I
declared completion Jun 2024 · SAI Sugandh Builders & Developers
Sugandhi Vihar Phase II
possession by Nov 2026 · SAI Vihar Builders AND Developers
Sukh Shanti Apartment
possession by Dec 2026 · Saimirra Realty
Sukhkarta
possession by Mar 2027 · Sukhkarta Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026