SUGANDHI VIHAR PHASE I

Palghar · SAI SUGANDH BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000005105

Delivery and registration

When is the project declared for completion?

SUGANDHI VIHAR PHASE I is registered with MahaRERA as P99000005105 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000005105
Registered on09 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUGANDHI VIHAR PHASE I record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Sugandh Builders is the promoter of record on 5 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SUGANDHI VIHAR PHASE I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO 11G+431 Dec 2019
BUILDING NO 21G+331 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2023The Delay was due to this project is under high speed rail project, and only building no. 1 is to be constructed and remaining buildings in this project compulsorily acquired under

Location, Land & Connectivity

Located at Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by SURVEY NO 150 155, to the south by BOISAR CHILLAR ROAD, to the east by SURVEY NO 157 A PART SURVEY NO 158 and to the west by SURVEY NO 148 149. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~73 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ73 km
Powai / Hiranandani business park75 km
Chhatrapati Shivaji Int'l Airport77 km
Bandra Kurla Complex (BKC)80 km
Lower Parel / Worli business district87 km
Nariman Point / Fort95 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Sukh Shanti Apartment
possession by Dec 2026 · Saimirra Realty
Sukhkarta
possession by Mar 2027 · Sukhkarta Developers
Sumitra Enclave Tower
possession by Dec 2027 · Sumitralandmark Private Limited
Sumitra Landmark Tower
possession by Dec 2027 · Sumitra Landmark Enterprises
SUN Heights
declared completion Dec 2024 · SUN Vinay Unique Realty LLP
Suncity Complex
declared completion Mar 2019 · Swastik Builder AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.