Mumbai/Project record

MahaRERA · the public record

Suncity Complex

Manor · SWASTIK BUILDER AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000009723

Delivery and registration

When is the project declared for completion?

Suncity Complex is registered with MahaRERA as P99000009723 and the promoter has declared completion for 31 Mar 2019.

31 Mar 2019

declared completion

90months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000009723
Registered on22 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 90 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Suncity Complex record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Swastik Builder is the promoter of record on 134 projects registered with MahaRERA, 18 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

134projects

registered with MahaRERA

18flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Suncity Complex in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Suncity Complex Type-C1G+431 Mar 2019
Suncity Complec Type-E1G+3-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Manor, Thane, Thane, 401403. Per the filed land record, the plot is bounded to the north by Gut No 36, to the south by State Highway Road, to the east by Gut No 32 and to the west by Gut No 35. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~66 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ66 km
Powai / Hiranandani business park67 km
Chhatrapati Shivaji Int'l Airport70 km
Bandra Kurla Complex (BKC)73 km
Lower Parel / Worli business district81 km
Nariman Point / Fort89 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Manor

15 Manor - Belvedere 2
possession by Dec 2026 · RV Infra
Myzo Suites Building NO 3 - A Wing
Not filing quarterly progress reports · possession by Dec 2027 · Ayush Reality
Myzo Suites Building NO 3 - B Wing
Not filing quarterly progress reports · possession by Dec 2027 · Shree Sadguru Developers
Godrej Country Estate
declared completion Apr 2026 · Godrej Projects Development Limited
Bandhan Heritage Phase II
Not filing quarterly progress reports · declared completion Dec 2025 · Mahi Links
Riddhi Siddhi Park Phase-2
Past its declared completion date · declared completion Jun 2024 · Riddhi Siddhi Builders

Other RERA-registered projects in Palghar

Sundar Heights
possession by Dec 2028 · Not Available
Sunrise Apt
possession by Dec 2026 · Paradise Developers
Sunrise Park
possession by Dec 2029 · Sunrise Developers
Sunshine Complex
declared completion Jun 2026 · Aditi Developers
Sunshine Complex
declared completion Dec 2023 · Mukesh Bhageloo Mishra
Sunshine Enclave
possession by Dec 2027 · Shantee Homes Realty LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026