MahaRERA Property Intelligence · Palghar

SUN HEIGHTS

P99000012242 · DONGRE VILLAGE · promoter Sun Vinay Unique

Certificate SignedDue 29 Dec 2024

Delivery & Registration

MahaRERA registrationP99000012242
Registered on01 Sep 2017
Promoter-declared completion29 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sun Vinay Unique is the promoter of record on 129 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
SUN HEIGHTS1G+1615 Aug 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202429 Dec 2024Due to shortage of material and labor not able to complete project please grant us extension till 29/12/2024

Location, Land & Connectivity

Located at DONGRE VILLAGE, CHIKHAL DONGRE ROAD, Borivali, Mumbai Suburban, 401303. Per the filed land record, the plot is bounded to the north by RG, to the south by 9 METER ROAD, to the east by ADJOINING BUILDING 2 WING A and to the west by ADJOINING BUILDING 2 WING C. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~38 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ38 km
Powai / Hiranandani business park40 km
Chhatrapati Shivaji Int'l Airport43 km
Bandra Kurla Complex (BKC)45 km
Lower Parel / Worli business district52 km
Nariman Point / Fort60 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar West

Padman Residency
Not filing quarterly progress reports · possession by Jul 2026 · Hemant Parshuram Bhoir
Vinay Unique Residency Bldg NO 7
possession by Sep 2026 · Jasamrit Estates Private Limited
Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers

Major developers building in Virar West

Other RERA-registered projects in Palghar

Suncity Complex
declared completion Mar 2019 · Swastik Builder AND Developers
Sundaram Plaza
declared completion Mar 2022 · A V Corporation
Sundaram Plaza H Wing
possession by Dec 2026 · Nine Realty Developers
Sundaram Plaza Wing A AND B
declared completion Dec 2023 · Parshvanath Developers
Sundaram Plaza Wing C
declared completion Dec 2021 · S.F Realtors
Sunny Plaza
declared completion Feb 2023 · Sunny Mathew Mathew

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026