MahaRERA Property Intelligence · Mumbai Suburban

TANDICE

P51800010353 · promoter Manish Mahesh Dholakia

Certificate SignedDue 30 Sep 2025

Delivery & Registration

MahaRERA registrationP51800010353
Registered on24 Aug 2017
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
TANDICE1G+830 Jan 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Dhindhoshi Court19652012Settlement Consent Term To Be Executed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Jul 202330 Jul 2020As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.07.2019 as the project completion date. However, we were not ab
31 Jul 202331 Jan 2023The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprec
31 Jul 201930 Sep 2025The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprec

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400067. Per the filed land record, the plot is bounded to the north by 6, to the south by 6, to the east by 9 and to the west by 9. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Primrose
possession by Jul 2026 · Kaustubh Construction Private Limited
Harmony
possession by Aug 2026 · Shreenath Associates
Laxmi Heights
possession by Sep 2026 · M/S Laxmi Lifespaces
Mahavir Majesty
possession by Sep 2026 · Mahavir Builders
Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon

Major developers building in Kandivali West

Other RERA-registered projects in Mumbai Suburban

Tandice69
declared completion Dec 2024 · Right Channel Construction PVT LTD
Tanishkaa Vikrant
possession by Jun 2029 · Tanishka Reality LLP
Tanishq Residency
declared completion Dec 2025 · Prathamesh Developers
Tanna Heights
declared completion Dec 2023 · Tanna Housing
Tanna Premises Veena Smart Homes
declared completion Dec 2024 · Tanna Infra Developers LLP
Tapodhan
possession by Dec 2026 · Gurukul Realty LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026