Mumbai/Project record

MahaRERA · the public record

Thakur Nagari Type D

Pasthal · Pawan Abhimanyu Singh

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000022978

Delivery and registration

When is the project declared for completion?

Thakur Nagari Type D is registered with MahaRERA as P99000022978 and the promoter has declared completion for 30 Oct 2023.

30 Oct 2023

declared completion

35months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000022978
Registered on06 Nov 2019
Promoter-declared completion30 Oct 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Thakur Nagari Type D record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Pawan Abhimanyu Singh is the promoter of record on 26 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

26projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Thakur Nagari Type D in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Thakur Nagari Building No 31G+431 Oct 2022

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Thakur Nagari Type D, with orders passed in 1 of them.

2complaints

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000033388605/01/2023DILIP RINDAVAN PATAR vs Mrs. Beena Singh @ Beena Pawankumarorder passed
CC1260422906/07/2026Omprakash Bholanath Sharma vs Pawan Abhimanyu Singhpending / no order on file

Location, Land & Connectivity

Located at Pasthal, Pasthal, Palghar, Palghar, 401501. Per the filed land record, the plot is bounded to the north by Building No 4, to the south by Internal Layout Road, to the east by Building No 6 and to the west by Building No 2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pawan Abhimanyu Singh is the promoter on 20 MahaRERA-registered projects, of which 12 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Pawan Abhimanyu Singh project & its RERA track record →

Other flagged projects by Pawan Abhimanyu Singh

Pawan Abhimanyu Singh
FlaggedPalghar
Pawan Abhimanyu Singh
FlaggedPalghar
Pawan Abhimanyu Singh
Past its declared completion datePalghar
Pawan Abhimanyu Singh
Past its declared completion datePalghar
Pawan Abhimanyu Singh
Past its declared completion datePalghar
Pawan Abhimanyu Singh
Past its declared completion datePalghar

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

THE Corner
declared completion Dec 2020 · Hemant Ramesh Mhatre
THE Curve
possession by Jun 2031 · Abhinav Realty Spaces LLP
THE Empire
declared completion Mar 2026 · Shahji Infra
The Great Western Mumbai
possession by Dec 2029 · Hoabl Impactum Land Private Limited
The Great Western Mumbai Building No. 11 - Prime
possession by Jun 2031 · Hoabl Impactum Land Private Limited
The Heaven-1
possession by Mar 2028 · OM Gayatri Builder AND Developer

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026