THARWANIS MEGHNA MONTANA PHASE - 3

AMBERNATH · THARWANI CONSTRUCTIONS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700055468

Delivery and registration

When is the project declared for completion?

THARWANIS MEGHNA MONTANA PHASE - 3 is registered with MahaRERA as P51700055468 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700055468
Registered on22 Mar 2024
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THARWANIS MEGHNA MONTANA PHASE - 3 record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Tharwani Constructions is the promoter of record on 50 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

50projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THARWANIS MEGHNA MONTANA PHASE - 3 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
K WING1G+17-
O WING1G+18-
R WING1G+11-
S WING1G+12-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Kalyan Civil Judge Senior Division842013Pending
Kalyan Civil Judge Senior Division3242016Pending

Location, Land & Connectivity

Located at AMBERNATH, BARVI DAM ROAD, Ambarnath, Thane, 421506. Per the filed land record, the plot is bounded to the north by SURVEY NO 135-2, to the south by SURVEY NO 139, to the east by SURVEY NO 140 and to the west by SURVEY NO 133. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park34 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district46 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tharwani Constructions PVT LTD is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Tharwani Constructions PVT LTD

Tharwani Constructions PVT LTD
FlaggedThane

Other RERA-registered projects in Ambarnath

Empire Industrial Centrum Phase 6
Deregistered by MahaRERA · possession by Oct 2026 · Empire Industries LTD
Empire Industrial Centrum Phase 5
possession by Jun 2027 · Empire Industries LTD
MID-Town
possession by Jun 2028 · Siddhivinayak Group NX
Precious Infinity
possession by Dec 2028 · RKR Construction
Sai Prasad Apartment
possession by Apr 2029 · Not Available
SPM Dream City Phase 2
possession by Dec 2030 · Swastik Lifespace

Other RERA-registered projects in Thane

THE Address Bldg. NO. 1
possession by Dec 2028 · Strawberry Constructions Pvt. Ltd.
THE Address Bldg. NO. 6
possession by Dec 2027 · Strawberry Constructions Pvt. Ltd.
THE Address Building NO. 2
possession by Dec 2026 · Strawberry Constructions Pvt. Ltd.
THE Address Building NO. 3
possession by Dec 2026 · Strawberry Constructions Pvt. Ltd.
THE Address Building No.4
possession by Dec 2026 · Strawberry Constructions Pvt. Ltd.
THE Address Building No.5
possession by Dec 2028 · Strawberry Constructions Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.