MahaRERA Property Intelligence · Mumbai Suburban

THE LEGEND

P51800052119 · PALI HILL · promoter Black Rock

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51800052119
Registered on24 Jul 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Black Rock is the promoter of record on 10 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 17 homes filed with MahaRERA, 7 are sold/booked (2 with registered agreements + 5 booked) and 10 remain available (~41% sold) — selling steadily. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101 & 2013,415 sqft (317.31 sqm)-
Floor 11023,266 sqft (303.4 sqm)-
Floor 3301 & 4013,261 sqft (302.94 sqm)-
Floor 33022,785 sqft (258.75 sqm)-
Floor 44022,785 sqft (258.75 sqm)-
Floor 6503 & 6033,658 sqft (339.83 sqm)-
Floor 7701 & 8013,212 sqft (298.38 sqm)-
Floor 77022,785 sqft (258.75 sqm)-
Floor 7703 & 8033,254 sqft (302.33 sqm)-
Floor 88022,785 sqft (258.75 sqm)-

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 17 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
THE LEGEND by Ashar1G+101731 Dec 2027

Unit mix on the filing: 17 residential.

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
SM1260017123/03/2026Bhakti Achrekar vs BLACK ROCKorder passed

Location, Land & Connectivity

Located at PALI HILL, NARGIS DUTT ROAD, Thane, Thane, 400050. Per the filed land record, the plot is bounded to the north by NARGIS DUTT ROAD, to the south by LAND BREEZE BUILDING, to the east by SAMEER BUILDING and to the west by SAMSHIBA BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport5 km
Lower Parel / Worli business district8 km
Andheri MIDC / SEEPZ8 km
Powai / Hiranandani business park10 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bandra West

The Wave
possession by Jul 2026 · Webtech Realty LLP
The Waterfront
possession by Aug 2026 · M/s Orbit Developers
Bandra Boon CHS LTD
possession by Sep 2026 · Mass Jaks Associate Ventures
Aryan Tower
Not filing quarterly progress reports · possession by Dec 2026 · Suchit Developers
Brightland
possession by Dec 2026 · Sambhavparshva Developers Private Limite
DLH Signature
possession by Dec 2026 · Flowline Developers Pvt Ltd

Major developers building in Bandra West

Other RERA-registered projects in Mumbai Suburban

THE Legend
possession by Sep 2026 · Empire Maitri Flora Constructions LLP
The Legend
possession by Jun 2028 · Ashapura United
THE Lisa
declared completion May 2025 · Shethwala Infra
THE Mansion
possession by Sep 2028 · Not Available
The Marque
possession by Oct 2028 · Gurukrupa Realcon Infrabuild LLP
THE Meadows
declared completion Nov 2019 · Guruashish Construction Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026