MahaRERA Property Intelligence · Raigarh

The Serenes Villa No 8

P52000012883 · promoter Mahindra Lifespaces

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP52000012883
Registered on07 Sep 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
The Serenes Villa No 81G+1-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Ward GSouth, Mumbai City, 402202. Per the filed land record, the plot is bounded to the north by 12 Mtr wide Internal Road, to the south by Gat no 1895, to the east by Villa No 9 and to the west by Villa No 7. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~44 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort36 km
Lower Parel / Worli business district44 km
Bandra Kurla Complex (BKC)51 km
Chhatrapati Shivaji Int'l Airport54 km
Powai / Hiranandani business park57 km
Andheri MIDC / SEEPZ58 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahindra Lifespace Developers Limited is the promoter on 65 MahaRERA-registered projects, of which 15 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mahindra Lifespace Developers Limited project & its RERA track record →

Other flagged projects by Mahindra Lifespace Developers Limited

Mahindra Lifespace Developers Limited
Deregistered by MahaRERAMumbai Suburban
Mahindra Lifespace Developers Limited
Deregistered by MahaRERAMumbai Suburban
Mahindra Lifespace Developers Limited
FlaggedPalghar
Mahindra Lifespace Developers Limited
FlaggedPalghar
Mahindra Lifespace Developers Limited
FlaggedPalghar
Mahindra Lifespace Developers Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Raigarh

Coral Paradise
possession by Dec 2027 · OM Prasan Construction LLP
Araaya
possession by Mar 2028 · Dream Homes

Other RERA-registered projects in Raigarh

The Serenes Villa No 9
declared completion Dec 2022 · Mahindra Lifespace Developers Limited
THE Signature
declared completion Dec 2024 · Horizon Buildmart
The Signature
possession by Dec 2029 · ARP Infra
THE Silver Crest
declared completion Sep 2024 · HI Tech Ultra Homes AND Infrastructure P
The Suites
declared completion Sep 2022 · Abhishek Agrawal
The Waterfront
declared completion Oct 2025 · Rajesh Mavillakandy Bhaskaran

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026