ALCOVE WING A

OPPOSITE SAKI VIHAR COMPLEX, CHANDIVALI · Mahindra Lifespace Developers limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800024919

Delivery and registration

When is the project declared for completion?

ALCOVE WING A is registered with MahaRERA as P51800024919 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800024919
Registered on12 Mar 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ALCOVE WING A record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ALCOVE WING A in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
ALCOVE WING A1G+1930 Jun 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at OPPOSITE SAKI VIHAR COMPLEX, CHANDIVALI, VILLAGE SAKI, OFF SAKI VIHAR ROAD, Ward GSouth, Mumbai City, 400072. Per the filed land record, the plot is bounded to the north by PROPOSED D P ROAD, to the south by DUNCUN INDUSTRIAL ESTATE, to the east by CLOSED INDUSTRIAL ESTATE S J STUDIO PART SLUM and to the west by EXISTING OFF SAKI VIHAR ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahindra Lifespace Developers Limited is the promoter on 65 MahaRERA-registered projects, of which 15 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Mahindra Lifespace Developers Limited project & its RERA track record →

Other flagged projects by Mahindra Lifespace Developers Limited

Mahindra Lifespace Developers Limited
Deregistered by MahaRERAMumbai Suburban
Mahindra Lifespace Developers Limited
FlaggedMumbai Suburban
Mahindra Lifespace Developers Limited
FlaggedMumbai Suburban
Mahindra Lifespace Developers Limited
FlaggedMumbai City
Mahindra Lifespace Developers Limited
FlaggedThane
Mahindra Lifespace Developers Limited
FlaggedThane

Other RERA-registered projects in Powai

55 Corporate Avenue Building NO 2
possession by Dec 2026 · THE Cannonade Construction Company PVT L
Ibis At L And T Realty Elixir Reserve
possession by Dec 2026 · Larsen & Toubro Ltd.
Leo Heights
Not filing quarterly progress reports · possession by Dec 2026 · Sir George P Joseph
Somani 72 East
possession by Dec 2026 · Nircon Developers PVT LTD
72 Marina - Phase I - Tierra And Torres
possession by Dec 2026 · D S Developers
Crescent Silverwoods
possession by Dec 2026 · Crescent Shelters

Major developers building in Powai

Other RERA-registered projects in Mumbai Suburban

Alcove Wing B
declared completion Jun 2024 · Mahindra Lifespace Developers Limited
Alena Residency Commercial
possession by Dec 2027 · Hemant Vinaykant Parikh
Alfa CO-Operative Housing Society LTD
possession by Dec 2027 · THE Green Venturez Developers
Alfa Padma Vasant
declared completion Jun 2026 · Zakiruddin Gaffar Sayyed
Alfred Splendour
possession by Dec 2027 · Barses Jawhar Anastasio Dsouza
Alliance Abhimanyu
possession by Feb 2027 · Alliance City Developers Realtors PVT LT

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026