Mumbai/Project record

MahaRERA · the public record

SOMANI 72 EAST

NEAR AERO CITY · NIRCON DEVELOPERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

84units filed as unsoldInventory · 19 September 2026
30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
84registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800051115

Delivery and registration

When is the project declared for completion?

SOMANI 72 EAST is registered with MahaRERA as P51800051115 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800051115
Registered on29 May 2023
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SOMANI 72 EAST record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Nircon Developers is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In SOMANI 72 EAST, ₹9.05 Cr of a declared ₹24.06 Cr estimated project cost is reported as incurred, about 37.6%, as at the last certified filing with MahaRERA.

37.6%

₹9.05 Cr

of ₹24.06 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SOMANI 72 EAST, 0 of 84 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 84 remain available.

0%sold

0 of 84 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SOMANI 72 EAST in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 September 2026

What the filings record, home by home

Read from MahaRERA on 19 September 2026

No home in SOMANI 72 EAST carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 84 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 16,451 a sq ft typical, over Rs 16,387 to Rs 20,480.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 84 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 84 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2 and 84 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
WING A COMMERCIAL1G+244-
WING A RESIDENTIAL1G+240-

Unit mix on the filing: 83 residential and 1 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2026Due to rainy season, shortage of material supply, shortage of labor the project was not able to get completed in time.

Location, Land & Connectivity

Located at NEAR AERO CITY, ANDHERI KURLA ROAD, Kurla, Mumbai Suburban, 400072. Per the filed land record, the plot is bounded to the north by EXISTING DP ROAD, to the south by CTS NO 646 PT AND CTS NO 651 PT, to the east by CTS NO 645 and to the west by CTS NO 651 PT. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport2 km
Powai / Hiranandani business park3 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ4 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Powai

55 Corporate Avenue Building NO 2
possession by Dec 2026 · THE Cannonade Construction Company PVT L
Ibis At L And T Realty Elixir Reserve
possession by Dec 2026 · Larsen & Toubro Ltd.
Leo Heights
Not filing quarterly progress reports · possession by Dec 2026 · Sir George P Joseph
72 Marina - Phase I - Tierra And Torres
possession by Dec 2026 · D S Developers
Crescent Silverwoods
possession by Dec 2026 · Crescent Shelters
Jangid Meadows
possession by Dec 2026 · Jangid Home PVT LTD

Major developers building in Powai

Other RERA-registered projects in Mumbai Suburban

Sona Heights
possession by Jul 2027 · Sumukha Realtors & Developers
Sonal Heights
declared completion Apr 2025 · Sonal DEV-CON PVT LTD
Soni Arcade, Building NO 2
declared completion Jun 2026 · Soni & Associates
SOS Developers
declared completion Dec 2024 · SOS Developers
Southfield Gravity
possession by Dec 2026 · Southfield Buildcon LLP
Sovenir
declared completion Jun 2022 · Suncity Corporation

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026