MahaRERA · the public record
THE X GHATKOPAR
AMAR MAHAL JUNCTION · ARIHANT REALTORS
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800025235
Delivery and registration
When is the project declared for completion?
THE X GHATKOPAR is registered with MahaRERA as P51800025235 and the promoter has declared completion for 30 Dec 2026.
30 Dec 2026
declared completion
3months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800025235 |
| Registered on | 23 Mar 2020 |
| Promoter-declared completion | 30 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 3 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THE X GHATKOPAR record 26 quarterly progress reports since registration.
26quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).
Promoter record
What else is this promoter on record for?
Arihant Realtors is the promoter of record on 142 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
142projects
registered with MahaRERA
14flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for THE X GHATKOPAR in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| THE X GHATKOPAR | 1 | G+19 | - |
Legal and disputes
What disputes are disclosed?
11 complaints are on the MahaRERA record for THE X GHATKOPAR, with orders passed in 9 of them.
11complaints
9with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000429369 | 21/02/2024 | Arihant Realtors vs Mr. Dashraj Egraj Modak & Mr. Egraj Nathubhai Modak | order passed |
| CC12400651 | 05/11/2024 | ARIHANT REALTORS vs Kirtikumar Umedchand Shah HUF | order passed |
| CC12500275 | 25/01/2025 | Shadilal and Sons vs ARIHANT REALTORS | order passed |
| CC12500274 | 25/01/2025 | Ajaykumar Abhaykumar Jain vs ARIHANT REALTORS | order passed |
| CC12502528 | 22/07/2025 | Sanjay Nenshi Nisar vs ARIHANT REALTORS | order passed |
| CC12502839 | 13/08/2025 | GAURAV BHANWARLAL GHATAWAT vs ARIHANT REALTORS | order passed |
| CC12503481 | 29/09/2025 | PANKAJ ROHIDAS SAWANT vs ARIHANT REALTORS | order passed |
| CC12600221 | 12/01/2026 | ARIHANT REALTORS vs Pankaj Rohidas Sawant | order passed |
| CC12600222 | 12/01/2026 | ARIHANT REALTORS vs Mr Nenshi Punja Nisar and Mr Sanjay Nenshi Nisar | order passed |
| CC12604111 | 01/07/2026 | ARIHANT REALTORS vs Mrs Hetal Chirag Patel | pending / no order on file |
| CC12604343 | 11/07/2026 | Hetal chirag Patel vs ARIHANT REALTORS | pending / no order on file |
Legal & Litigation
The promoter has declared 5 court cases on this project to MahaRERA. 5 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Mm Court | 20/N/15 | 2015 | Pending |
| Mm Court | 177/N/15 | 2015 | Pending |
| City Civil Court | 1001/2016 | 2016 | Pending |
| City Civil Court | 2295/2013 | 2013 | Pending |
| High Court | NM27/2018 IN WRIT PETITION 2534/2016 | 2017 | Pending |
Location, Land & Connectivity
Located at AMAR MAHAL JUNCTION , MG ROAD, Kurla, Mumbai Suburban, 400079. Per the filed land record, the plot is bounded to the north by 29 PT, to the south by 29 PT, to the east by 29 PT and to the west by DP ROAD. These are the boundaries as recorded in the filed land record.