MahaRERA Property Intelligence · Thane

TIRUPATI COMPLEX

P51700011047 · BHAYANDAR · promoter Tirupati Developers

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51700011047
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Tirupati Developers is the promoter of record on 156 projects, of which 10 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~43.1% of the estimated project cost incurred as of the last certificate (₹8.53 Cr spent against a ₹19.80 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 40 homes filed with MahaRERA, 34 are sold/booked (33 with registered agreements + 1 booked) and 6 remain available (~85% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹19.96 Cr in agreement value so far. Of that, ₹18.15 Cr (~91%) is already collected, ₹1.82 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 34 registered agreements, the effective carpet rate is ₹9,305/sqft (typical range ₹7,693–₹14,146) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1C-102718 sqft (66.66 sqm)₹42.40 Lakh
Floor 1D-106698 sqft (64.82 sqm)₹41.23 Lakh
Floor 2C-202718 sqft (66.66 sqm)₹42.40 Lakh
Floor 2C-204454 sqft (42.17 sqm)₹26.82 Lakh
Floor 4C-402718 sqft (66.66 sqm)₹42.40 Lakh
Floor 5C-504454 sqft (42.17 sqm)₹26.82 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 40 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
TIRUPATI COMPLEX BLDG 2 C AND D WING1G+540-

Unit mix on the filing: 40 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202731 Dec 2027AS REGARD TO RECEIVED COMMENCEMENT CERTIFICATE ATTACHED IN DOCUMENT UPLOAD SECTION, STILT + 5TH FLOOR REVISED PLAN IS APPROVED FROM MBMC. THEREFORE WE SEEK FOR EXTENSION OF PROJECT

Location, Land & Connectivity

Located at BHAYANDAR, NEAR RAILWAY STATION, Thane, Thane, 401101. Per the filed land record, the plot is bounded to the north by 1513 TO THE NORTH, to the south by VENKATESH PLAZA, to the east by RAILWAY and to the west by CTS NO 1484. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park22 km
Chhatrapati Shivaji Int'l Airport25 km
Bandra Kurla Complex (BKC)27 km
Lower Parel / Worli business district35 km
Nariman Point / Fort43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Tirupati Developers is the promoter on 67 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Tirupati Developers project & its RERA track record →

Other flagged projects by Tirupati Developers

Tirupati Developers
FlaggedPalghar

Other RERA-registered projects in Bhayander West

Anantsavitri Ratna Heights
possession by Aug 2026 · Krisha Realty
Bhairav Enclave
possession by Aug 2026 · Leena Estate Venture
Mukundam
possession by Aug 2026 · Shree Ramjeevdani Realtors
Saroj Chandra Krupa
possession by Oct 2026 · S C Associates
SAI Hanuman Tower
possession by Dec 2026 · Shree Samartha Developers
Chandanbala
possession by Dec 2026 · Hemant Sagarmal Jain

Other RERA-registered projects in Thane

Tirupati Heights
declared completion Dec 2023 · M/S Shri Tirupati Realty
Tirupati Heights
declared completion Jun 2024 · Tirupati Enterprises
Tirupati Heights
declared completion Mar 2025 · Tirupati Builders AND Developers
Tirupati Hieghts
declared completion Mar 2018 · Shri Tirupati Realty
Tirupati Namaah
possession by Dec 2030 · Om Shree Tirupati Balaji Builders
Tirupati Ritu Empire
possession by Dec 2029 · Ritu Corp

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026