MahaRERA Property Intelligence · Raigarh

TULSI V CITY - TULSI VIVAAN

P52000015825 · WANGANI-PASHANE · promoter Raj Realtors (A

Certificate SignedDue 31 Mar 2025

Delivery & Registration

MahaRERA registrationP52000015825
Registered on27 Mar 2018
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Building No 5 - A, B, C, D1G+831 Mar 2021
Building No 6 - A, B, C, D1G+831 Mar 2021
Building 7 - A and B1G+731 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 202530 Sep 2022The date of completion as per RERA record is 30/09/2021 (i.e. after the Suomoto Extension given by RERA Authorities).However the construction work is delayed due to less booking /
31 Mar 202531 Mar 2025That we have already obtained consent/NOC from more than 51% allotees at the time of applying last extention and our project is also completed in all respect, Now it is not possibl
31 Mar 202531 Mar 2024We have completed the construction and development work of all the buildings viz., (Building No.5,6 & 7 consisting 10 Wings) of our project Tulsi Vivaan in all respect. We have obt

Location, Land & Connectivity

Located at WANGANI-PASHANE, NA, Thane, Thane, 421503. Per the filed land record, the plot is bounded to the north by S NO 8 1, to the south by S NO 168 2B 3C B, to the east by S NO 9 2 B and to the west by ODR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~43 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park43 km
Andheri MIDC / SEEPZ47 km
Bandra Kurla Complex (BKC)47 km
Chhatrapati Shivaji Int'l Airport47 km
Lower Parel / Worli business district53 km
Nariman Point / Fort56 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Raigarh

Tulsi Vedant
possession by Dec 2028 · Shubh Developers
Tulsi Vihar
declared completion May 2022 · Pawan Developers
Turtle Sparsh
possession by Dec 2027 · Mehul Bharat Shah
Ubha Vitevari
declared completion Oct 2022 · OM Civil Constructions
Udaan Aria
possession by Dec 2027 · Udaan Builders And Developers
Udaan Avenue
declared completion Jul 2022 · Udaan Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026