Tycoons Valley Tower B

P51700049321 · Khadakpada · promoter Milestone Space

Certificate SignedDue 30 Jun 2025

Delivery & Registration

MahaRERA registrationP51700049321
Registered on07 Feb 2023
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 13 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Milestone Space is the promoter of record on 16 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 23 homes filed with MahaRERA, 0 are sold/booked and 23 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 10011,210 sqft (112.43 sqm)₹87.47 Lakh
Floor 1002288 sqft (26.73 sqm)₹20.80 Lakh
Floor 1003497 sqft (46.16 sqm)₹35.91 Lakh
Floor 1103706 sqft (65.57 sqm)₹58.69 Lakh
Floor 1301979 sqft (90.96 sqm)₹70.86 Lakh
Floor 20011,210 sqft (112.43 sqm)₹87.47 Lakh
Floor 2002288 sqft (26.73 sqm)₹20.80 Lakh
Floor 2003497 sqft (46.16 sqm)₹35.91 Lakh
Floor 22011,131 sqft (105.08 sqm)₹94.05 Lakh
Floor 2202580 sqft (53.91 sqm)₹48.25 Lakh
Floor 2203701 sqft (65.09 sqm)₹58.26 Lakh
Floor 3302618 sqft (57.38 sqm)₹44.70 Lakh
Floor 3303616 sqft (57.19 sqm)₹44.55 Lakh
Floor 4401979 sqft (90.96 sqm)₹70.86 Lakh
Floor 4402618 sqft (57.38 sqm)₹44.70 Lakh
Floor 4403616 sqft (57.19 sqm)₹44.55 Lakh
Floor 5501979 sqft (90.96 sqm)₹74.40 Lakh
Floor 5502618 sqft (57.38 sqm)₹46.93 Lakh
Floor 5503616 sqft (57.19 sqm)₹46.78 Lakh
Ground/Floor 00011,308 sqft (121.48 sqm)₹1.03 Cr
Ground/Floor 0002214 sqft (19.92 sqm)₹1.69 Cr
Ground/Floor 0003272 sqft (25.3 sqm)₹21.43 Lakh
Ground/Floor 0004563 sqft (52.3 sqm)₹44.30 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 23 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building 1 Wing B - Ruby1G+52330 Jun 2025

Unit mix on the filing: 9 residential and 14 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division2812010Ongoing

Location, Land & Connectivity

Located at Khadakpada, Godrej Hill, Kalyan, Thane, 421301. Per the filed land record, the plot is bounded to the north by 15 Meter Road, to the south by Reservation, to the east by 30 Meter Road and to the west by Tycoons Valley Tower A - Emerald. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8204 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort8203 km
Lower Parel / Worli business district8204 km
Chhatrapati Shivaji Int'l Airport8209 km
Bandra Kurla Complex (BKC)8209 km
Andheri MIDC / SEEPZ8210 km
Powai / Hiranandani business park8213 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/s. Milestone Space is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by M/s. Milestone Space

M/s. Milestone Space
FlaggedThane

Other RERA-registered projects in Kalyan

Tharwani Solitaire Phase IV
possession by Jul 2026 · Anil Hardasmal Tharwani
Kailash Gardens
possession by Jul 2026 · Shree Laxmi Enterprises
Mangeshi Ambar
possession by Jul 2026 · Mangesh Dashrath Gaikar
Mangeshi Tulip
possession by Jul 2026 · Mangesh Dashrath Gaikar
Anand 21 Uptown
possession by Aug 2026 · VPA Developers
Pawan Atharva Phase I
possession by Aug 2026 · Pawan Real Estate

Major developers building in Kalyan

Other RERA-registered projects in Thane

Type-B Redwood
declared completion Dec 2022 · RDC Ventures
Udaynagar Chs
possession by Mar 2028 · Natu Paranjape Realty
UMA Ananta
possession by Mar 2029 · UMA Infratech
Uma Ashish A Wing
declared completion Dec 2019 · Uma Housing
UMA Ashish B Wing
declared completion Jul 2018 · Parasiya Developes
UMA CHS LTD
possession by Dec 2030 · Yadav Bros Constructions

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026