MahaRERA Property Intelligence · Raigarh

V AASHRAYA

P52000017495 · PUSHPAKNAGAR · promoter Atharva Developers

Certificate SignedDue 30 Jul 2022

Delivery & Registration

MahaRERA registrationP52000017495
Registered on23 Aug 2018
Promoter-declared completion30 Jul 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Atharva Developers is the promoter of record on 83 projects, of which 12 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
V AASHRAY1G+431 Jul 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jul 202230 Jan 2022We hereby declare that original proposed date of completion as 31st January, 2021. However due to problems happening due to Covid-19 and due to lock down, we could not complete the

Location, Land & Connectivity

Located at PUSHPAKNAGAR, SECTOR R-4, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by PLOT NO 13, to the south by PLOT NO 11, to the east by PROPOSED 9 MTR ROAD and to the west by PLOT NO 4 AND 5. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Atharva Developers is the promoter on 19 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Atharva Developers project & its RERA track record →

Other flagged projects by Atharva Developers

Atharva Developers
FlaggedMumbai Suburban
Atharva Developers
FlaggedMumbai Suburban
Atharva Developers
FlaggedMumbai Suburban
Atharva Developers
FlaggedMumbai Suburban
Atharva Developers
FlaggedMumbai Suburban
Atharva Developers
Past its declared completion dateRaigarh

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

V Balaji Bless
declared completion May 2020 · V Reality
V M Heritage 2
declared completion Jan 2020 · Dilawar Sujatkhan Pathan
V M Residency
declared completion Jul 2024 · V M Developers
V Swasthik
declared completion Dec 2023 · Skyline Infrastructure
V Vastu
declared completion Sep 2021 · Atharva Developers
Vaastavya Residency
possession by Dec 2027 · Siddhivinayak Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026