MahaRERA Property Intelligence · Raigarh
P52000017673 · KOPROLI VILLAGE · promoter Sudam Nivrutti Bhor
| MahaRERA registration | P52000017673 |
| Registered on | 04 Sep 2018 |
| Promoter-declared completion | 30 Dec 2022 |
| Current status | Certificate Signed |
| Against today | about 43 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sudam Nivrutti Bhor is the promoter of record on 20 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| VEDANT RESIDENCY | 1 | G+5 | - |
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Dec 2022 | 30 Dec 2023 | As per phase 2 mentioned on the RERA website for the above project. we have now applied and processed for amended commencement certificate CIDCO/NAINA to utilize balance F.S.I (un |
| 30 Dec 2022 | 30 Dec 2024 | As per our earlier extension letter. We have now received the Ammended Commencement Certificate CC. No. : CIDCO/NAINA/Panvel/Koproli/BP-00121/ACC/2023/0430 Dated 13/09/2023. OCCUP |
Located at KOPROLI VILLAGE, PANVEL MATHERAN ROAD, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by GUT NO-11, to the south by GUT NO -7, to the east by FOREST and to the west by PANVEL MATHERAN ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in VEDANT RESIDANCY?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026