Mumbai/Project record

MahaRERA · the public record

Veena Velocity PH-II

Vasai-West · NIKUNJ DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000014147

Delivery and registration

When is the project declared for completion?

Veena Velocity PH-II is registered with MahaRERA as P99000014147 and the promoter has declared completion for 30 Sep 2020.

30 Sep 2020

declared completion

72months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000014147
Registered on09 Nov 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 72 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Veena Velocity PH-II record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nikunj Developers is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Veena Velocity PH-II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Wing - A1G+831 Mar 2019
Wing - B1G+831 Mar 2019
Wing - C1G+831 Mar 2019
Wing - D1G+831 Mar 2019
Wing - E1G+831 Mar 2019

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Veena Velocity PH-II, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019394207/09/2020Mr. Vilas Janardan Gode vs M/s. Nikunj Developersorder passed
CC00600000005799608/02/2019Mahesh Kumar Balmiki vs Haresh Sanghaviorder passed
CC00600000039607123/07/2023Mahesh Kumar Deep Kumar Balmiki vs NIKUNJ DEVELOPERSorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2020Dear Sir, We would like to inform you that Project having original date of completion was 31/03/2019 as mentioned in the declaration given in FORM-B and we have completed buildings

Location, Land & Connectivity

Located at Vasai-West, 100 feet Road, Vasai, Palghar, 401202. Per the filed land record, the plot is bounded to the north by Adjacent C T S No 27 112, to the south by Adjacent C T S No 115 116, to the east by Adjacent C T S No 113 114 and to the west by Adjacent C T S No 35 36. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ28 km
Powai / Hiranandani business park31 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district43 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nikunj Developers is the promoter on 3 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Nikunj Developers

Nikunj Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Vasai West

Happy Home Jasmine C D
possession by Sep 2026 · Happy Home Corporation
Dream Aura
possession by Dec 2026 · Clement Regency Developers
Vijaya Complex
Not filing quarterly progress reports · possession by Dec 2026 · Padmavati Enterprises
Ashoka Heavens
possession by Dec 2026 · Shree Mahashraman Realtors
Dattani Vertex Building No.4 Wing EF
possession by Dec 2026 · Brijesh Satish Dattani
Gokarna Residency
possession by Dec 2026 · Harshal Anil Acharya

Other RERA-registered projects in Palghar

Veer 11
possession by Mar 2027 · Veer Global Infraconstruction Limited
Veer Attar
possession by Mar 2028 · V A Housing
Veer One
possession by Dec 2027 · Veer Global Infraconstruction Limited
Vencel Enclave
possession by Dec 2029 · Rupali Vishal Dabre
Vibgyor Heights
possession by Dec 2029 · Emmanuel Developers
Vichare Vihar
declared completion Dec 2024 · Satish Balkrushna Vichare

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026