MahaRERA Property Intelligence · Mumbai Suburban

VICTORY PLATINUM

P51800008591 · promoter Prashanti Land Developers

Certificate SignedDue 31 Dec 2019

Delivery & Registration

MahaRERA registrationP51800008591
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 79 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
JINKU CHS LTD A WING1G+22-
JINKU CHS LTD B WING1G+20-
JINKU CHS LTD C WING1G+731 Dec 2018

Complaints & Orders

23 complaints are on the MahaRERA record for this project, with orders passed in 20. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000018201931/12/2019Mrs. Vijayshree Ajay Pandya vs Himanshu Shah - Prahsanti Lan Developers Pvt Ltdorder passed
CC00600000019471104/11/2020Hinduja Leyland Finance Ltd vs Prashanti land Developers Pvt Ltdorder passed
CC00600000019553015/01/2021SAMIR MANSUKH SANGOI vs Prashanti Land Developers Private Limitedorder passed
CC00600000019574625/01/2021SHAILESH HIMMATLAL SHUKLA & REENA SHAILESH SHUKLA vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019592107/02/2021PANKAJ S. VIRA/ASHA P. VIRA/CHIRAG P. VIRA vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019592707/02/2021LEEPA/JATIN/JAIMIN MEHTA vs PRASHANTI LAND DEVELOPERS PVT. LTD.order passed
CC00600000019592007/02/2021Ajay Hasmukh Vastani vs Prashanti Land Developers Private Limitedorder passed
CC00600000019592307/02/2021MEERA KETAN DHAKAN vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019592407/02/2021Hitesh Rasiklal Kadakia vs Prashanti Land Developers Private Limitedorder passed
CC00600000019592607/02/2021KETAN VINOD DHAKAN vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019592807/02/2021DHIRENDRA HARKISANDAS SHAH vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019592907/02/2021Saumil Rohit Kadakia vs Prashanti Land Developers Private Limitedorder passed
CC00600000019602114/02/2021Sandhya Prakash Unadkat vs Prashanti Land Developers Private Limitedorder passed
CC00600000019602614/02/2021NILESH BHAVARLAL CHOPRA/BHAVARLAL S CHOPDA/PUSHPA B CHOPDA vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019602314/02/2021ARTI PINAKIN SHUKLA/PINAKIN SHUKLA vs PRASHANTI LAND DEVELOPERS PVT LTDorder passed
CC00600000019602714/02/2021Pavan Navinchandra Lakhani vs Prashanti Land Developers Private Limitedorder passed
CC00600000019602514/02/2021GEETA MAHENDRA JAIN/MAHENDRA J. JAIN/KINNARI M. JAIN vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019611321/02/2021MANISH VIPIN DESAI/BAKULA BHARAT SHAH/HETAL MANISH DESAI vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000019638017/03/2021ALOK SHAH vs Prashanti land developers Pvt ltdorder passed
CC00600000019658301/04/2021VICTORY PLATINUM B WING ALLOTTEES ASSOCIATION vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDorder passed
CC00600000021004017/02/2022JIGNA PARESH SHAH vs PRASHANTI LAND DEVELOPERS PVT. LTD.pending / no order on file
CC00600000030338921/11/2022ARHAM GLOBAL SERVICES LLP vs GEETA MAHENDRA JAINpending / no order on file
CC1250196116/06/2025Rajyog Corporations vs PRASHANTI LAND DEVELOPERS PRIVATE LIMITEDpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Dindoshi22002016Suit Ongoing
High Court Of Judicature Of Bombay9362016Closed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201931 Dec 2019FINISHING WORK IS PENDING DETAILED FACTS, REASONS AND PRAYER IS ATTACHED UNDER OTHER TAB

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by BHAGAT NIWAS AND GOPAL NIWAS, to the south by VATSAL CHS AND VIDHYA VINAY CHS, to the east by GANESH MANISH CHS SV ROAD and to the west by JYOTI PARK RAJ ASHISH CHS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park11 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali West

Primrose
possession by Jul 2026 · Kaustubh Construction Private Limited
Harmony
possession by Aug 2026 · Shreenath Associates
Laxmi Heights
possession by Sep 2026 · M/S Laxmi Lifespaces
Mahavir Majesty
possession by Sep 2026 · Mahavir Builders
Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon

Major developers building in Kandivali West

Other RERA-registered projects in Mumbai Suburban

Victory Stella Nestle
possession by Jun 2028 · Victory Venture Developers
Vidhya Darshan
declared completion Feb 2021 · Aditya Enterprises
Vidya Nidhi
declared completion Mar 2024 · Laxmi Aakar Realty
Vidyalankar Chsl
possession by Jul 2026 · Desai Residency Private Limited
Viera Golf Greens
possession by Mar 2032 · Nensee Constructions Private Limited
Viewstone
declared completion Dec 2025 · Kherectors LLP

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026