Mumbai/Project record

MahaRERA · the public record

VIDYA VIHAR

NEAR RAILWAY PHATHAK · ACORN BUILDER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000030797

Delivery and registration

When is the project declared for completion?

VIDYA VIHAR is registered with MahaRERA as P99000030797 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000030797
Registered on13 Sep 2021
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIDYA VIHAR record 8 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 8 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Acorn Builder is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for VIDYA VIHAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
VIDYA VIHAR1G+430 Jun 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NEAR RAILWAY PHATHAK, CHINCHANI ROAD, Thane, Thane, 401103. Per the filed land record, the plot is bounded to the north by LAND SR NO-38, to the south by LAND SR NO 39-1, to the east by LAND SR NO-38 and to the west by ADJ NALA. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vangaon

Ekta Parksville Phase II
possession by Dec 2026 · Ekta Parksville Homes Pvt. Ltd.
Galaxy Residency
Not filing quarterly progress reports · possession by Dec 2026 · Mahashakti Enterprises
Tanishq H AND I Wing
possession by Dec 2026 · Puneet Developers
Ivory Homes
possession by Jul 2027 · Yashron Developers LLP
Prime ONE
possession by Dec 2027 · Primeville Developers LLP
Tanishq Type G-5,e-5,f-5 Wing P,q,r
possession by Dec 2027 · Rajvan Lifespaces LLP

Other RERA-registered projects in Palghar

Vijay Apartment Chsl
declared completion May 2025 · Casa Builders AND Developers
Vijaya Complex
possession by Dec 2026 · Padmavati Enterprises
Vikas Dynasty II
possession by Dec 2028 · Vikas Tukaram Patil
Vikas Industries - 1
declared completion Mar 2022 · Vinayak Enterprises
Vikas Industries - 2
declared completion Apr 2022 · Vinayak Enterprises
Vimal Classic
possession by Dec 2026 · OM Vimal Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026