0units filed as unsoldInventory · 18 September 2026
30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
185registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700024245

Delivery and registration

When is the project declared for completion?

VIRAT GRANDEUR is registered with MahaRERA as P51700024245 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700024245
Registered on29 Jan 2020
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIRAT GRANDEUR record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Deiv Enterprises is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In VIRAT GRANDEUR, 136 of 136 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

136 of 136 homes

₹74.08 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹73.69 Cr (about 99%) is recorded as collected and ₹0 as receivable. The project registers 185 homes in total, while this sold/unsold inventory filing covers 136 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 136 registered agreements, the effective carpet rate is ₹11,340/sqft, with eight in ten falling between ₹10,198 and ₹13,732 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 49 owner/investor-held.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 136 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in VIRAT GRANDEUR is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 136 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 136 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20 and 185 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Virat Grandeur1G+2018531 Dec 2024

Unit mix on the filing: 150 residential and 35 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for VIRAT GRANDEUR, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
SM1260014416/02/2026Bhakti Achrekar vs DEIV ENTERPRISESorder passed

Location, Land & Connectivity

Located at Kanchangaon, Nr Manjunath College, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by 18 Mtr DP Road, to the south by Survey no 70 hissa 4, to the east by 24 Mtr DP Road and to the west by Survey no 69. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~24 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park24 km
Andheri MIDC / SEEPZ27 km
Chhatrapati Shivaji Int'l Airport29 km
Bandra Kurla Complex (BKC)30 km
Lower Parel / Worli business district38 km
Nariman Point / Fort44 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Deiv Enterprises is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Dombivli East

Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel
Sumati Skyline
possession by Sep 2026 · Subhash Skyline Infra
Vinayak Prerana
possession by Sep 2026 · Nakshatra Group
Shanu Majestic
possession by Dec 2026 · Fortune Group Of Construction
Balaji Annex
possession by Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders

Major developers building in Dombivli East

Other RERA-registered projects in Thane

Virat Skyros
possession by Dec 2030 · Param Developers
Virat Vastu-2
possession by Dec 2028 · Shreeji Realty
Visava
declared completion Dec 2025 · M/s Rudrik Developers
Vishal Height A Wing
declared completion Dec 2022 · Vishal Corporation
Vishnu Altezza
possession by Dec 2027 · Vishnu Infra
Vishnu Bliss
declared completion Jun 2026 · Legacy Builders & Innovators

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026