Mumbai/Project record

MahaRERA · the public record

VIVIANA - BLOCK 5

VIVIANA PROJECT · NIRMAN REALTORS AND DEVELOPERS LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10units filed as unsoldInventory · 16 September 2026
30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
32registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000006209

Delivery and registration

When is the project declared for completion?

VIVIANA - BLOCK 5 is registered with MahaRERA as P52000006209 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000006209
Registered on14 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VIVIANA - BLOCK 5 record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

How much has actually been sold?

In VIVIANA - BLOCK 5, 22 of 32 homes filed with MahaRERA are recorded as sold or booked (21 with registered agreements and 1 booked), about 69%, and 10 remain available.

69%sold

22 of 32 homes

₹3.60 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹3.39 Cr (about 94%) is recorded as collected and ₹21.29 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1A3,638 sqft (337.99 sqm)₹15.42 Lakh
Floor 1A - 1023,638 sqft (337.99 sqm)₹15.42 Lakh
Floor 1A - 1043,456 sqft (321.09 sqm)₹14.65 Lakh
Ground/Floor 0A - 033,240 sqft (301 sqm)₹13.73 Lakh
Ground/Floor 0A - 043,240 sqft (301 sqm)₹13.73 Lakh
Ground/Floor 0A -053,240 sqft (301 sqm)₹13.73 Lakh
Ground/Floor 0B -012,120 sqft (197 sqm)₹8.98 Lakh
Ground/Floor 0B -023,240 sqft (301 sqm)₹13.73 Lakh
Ground/Floor 0B -043,057 sqft (284 sqm)₹12.96 Lakh
Ground/Floor 0B -053,240 sqft (301 sqm)₹13.73 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 22 homes carry one, and 10 of the 32 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
A 3,638 sqftRs 13.00 lakh typical, over Rs 11.16 lakh to Rs 28.00 lakh12 filed on this stack, floors 1–3

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In VIVIANA - BLOCK 5, 3 of the 10 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 9 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 32 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
VIVIANA - BLOCK 51G+432-

Unit mix on the filing: 32 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for VIVIANA - BLOCK 5, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250036903/02/2025BRIJESH BRIJBHUSHAN DUBEY vs NIRMAN REALTORS AND DEVELOPERS LTDorder passed

Location, Land & Connectivity

Located at VIVIANA PROJECT, NISARG NIRMAN, Andheri, Mumbai Suburban, 410201. Per the filed land record, the plot is bounded to the north by Open, to the south by 20 Road, to the east by Open Space and to the west by Plot No 43. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~45 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park45 km
Bandra Kurla Complex (BKC)48 km
Chhatrapati Shivaji Int'l Airport49 km
Andheri MIDC / SEEPZ49 km
Lower Parel / Worli business district52 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nirman Realtors AND Developers LTD is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Nirman Realtors AND Developers LTD project & its RERA track record →

Other flagged projects by Nirman Realtors AND Developers LTD

Nirman Realtors AND Developers LTD
FlaggedMumbai Suburban
Nirman Realtors AND Developers LTD
FlaggedRaigarh
Nirman Realtors AND Developers LTD
FlaggedMumbai Suburban
Nirman Realtors AND Developers LTD
FlaggedRaigarh

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

VLC Pride
declared completion Dec 2024 · Shiv Trident Buildcon LLP
Vrinda VAN
declared completion Dec 2025 · Shivkrupa Realty
Vrindavan
possession by Jun 2028 · S P Construction
Vrindavan Apartments Phase I
declared completion Nov 2020 · Palnitkar AND Gandhi Constructions LLP
Vrindavan Chandar Heights
possession by Mar 2027 · Vrindavan Developers
Vrindavan Flora
possession by Dec 2028 · Thalia Labh Home Makers Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026