Mumbai/Project record

MahaRERA · the public record

Vrindavan Apartments Phase I

Ris · PALNITKAR AND GANDHI CONSTRUCTIONS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000016726

Delivery and registration

When is the project declared for completion?

Vrindavan Apartments Phase I is registered with MahaRERA as P52000016726 and the promoter has declared completion for 30 Nov 2020.

30 Nov 2020

declared completion

70months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000016726
Registered on05 Jun 2018
Promoter-declared completion30 Nov 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vrindavan Apartments Phase I record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vrindavan Apartments Phase I in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Building 21G+431 May 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Ris, Behind Church, Khalapur, Raigarh, 410222. Per the filed land record, the plot is bounded to the north by plot no 8, to the south by plot no 13-1b, to the east by Plot no 13-2 and to the west by plot no 9-2. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Rees

Balaji Tulips
possession by Nov 2026 · Balaji Homes
Latitude-Status Redefined
possession by Dec 2026 · Flexton Lifespaces Private Limited
Jyoti Residency
possession by Mar 2027 · Janvi Enterprises
Shree Aangan - A Wing
possession by Dec 2027 · Shiv Creators LLP
Triratna Complex
possession by Dec 2027 · Empire Builders AND Developers
Aashray Nisarg
possession by Jun 2028 · Aashray Homes

Other RERA-registered projects in Raigarh

Vrindavan Chandar Heights
possession by Mar 2027 · Vrindavan Developers
Vrindavan Flora
possession by Dec 2028 · Thalia Labh Home Makers Private Limited
Vrindavan Flora
possession by Dec 2028 · Thalia Vastu Infra Projects
Vrindavan Flora - Phase III - Bldg NO - 4
possession by Dec 2027 · Thalia Vastu Infra Projects
Vrindavan Flora-Rasayani Garden-Phase I
declared completion Dec 2021 · Thalia Labha Home Private Limited
Vrindavan Heights
possession by Dec 2033 · Sahajanand Infratech

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026