Mumbai/Project record

MahaRERA · the public record

Vrindavan

OPP OBEROI MALL · JE AND VEE INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800017298

Delivery and registration

When is the project declared for completion?

Vrindavan is registered with MahaRERA as P51800017298 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800017298
Registered on31 Jul 2018
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Vrindavan record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Vrindavan in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
Vrindavan1G+2231 Dec 2023

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Vrindavan, with orders passed in 0 of them.

2complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039632119/06/2023Mr. Vinay Singh vs Neha Patilpending / no order on file
CC00600000039632219/06/2023Mr. Vinay Singh vs Nilesh Patilpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court102812019Disposed
Supreme Court Of India129962019Disposed

Location, Land & Connectivity

Located at OPP OBEROI MALL, BUILDING NO 15 SHIVDHAM COMPLEX DINDOSHI MALAD EAST, Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by BY BLDG NO 16, to the south by BY BULD NO 14 AND NALLA, to the east by BLDG NO 13 AND 9 14 MTR ROAD and to the west by BY BLDG NO 17. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

JE AND VEE Infrastructure is the promoter on 9 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every JE AND VEE Infrastructure project & its RERA track record →

Other flagged projects by JE AND VEE Infrastructure

JE AND VEE Infrastructure
FlaggedMumbai Suburban
JE AND VEE Infrastructure
FlaggedMumbai Suburban
JE AND VEE Infrastructure
FlaggedMumbai Suburban
JE AND VEE Infrastructure
FlaggedMumbai Suburban

Other RERA-registered projects in Malad East

Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd
Royal Pristo
possession by Dec 2026 · Royal Realtors
Spring Meadows
possession by Dec 2026 · Renaissance Enterprises

Other RERA-registered projects in Mumbai Suburban

Vrindavan Elite
possession by Oct 2026 · Matrix Constructions
Vrundavan
declared completion Apr 2026 · Abhar Properties Private Limited
Vrundavan SRA CHS LTD Lotus Tower
declared completion Mar 2026 · Shree Varadkrupa Towers LLP
Vrushali Villa
declared completion Dec 2019 · Aditya Associates
Wadhwa 723 Avenue
declared completion May 2026 · Harshvardhan Constructions
West Avenue
declared completion Mar 2026 · M/s Dhabalia Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026