MahaRERA Property Intelligence · Raigarh

WHITE NEST

P52000018075 · NODE ULWE · promoter Supertech

Certificate SignedDue 31 Dec 2022

Delivery & Registration

MahaRERA registrationP52000018075
Registered on10 Oct 2018
Promoter-declared completion31 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Supertech is the promoter of record on 6 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
WHITE NEST1G+11-

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000047988730/04/2024SANTOSH SHAMRAO KATE vs SHAGUN SUPERTECH LLPpending / no order on file
CC1250342225/09/2025Abhimanyu Balaram Patil vs SHAGUN SUPERTECH LLPpending / no order on file
CC1250343326/09/2025Abhimanyu Balaram Patil vs SHAGUN SUPERTECH LLPpending / no order on file
CC1260078011/02/2026Sajith Sadasivan vs SHAGUN SUPERTECH LLPpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202231 Dec 2023The RERA Registration No was granted on 08.10.2018, however work could not be commenced because of some local issues. The construction work is started from 06.04.2019, considering

Location, Land & Connectivity

Located at NODE ULWE, SECTOR 20, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by 24 MTR WIDE ROAD, to the south by PLOT NO 140-156-155-154, to the east by PLOT NO 143 and to the west by 11 MTR WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Shagun Supertech LLP project & its RERA track record →

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

White OAK
declared completion Apr 2025 · Amber Buildcon
White Square
declared completion Dec 2025 · JNS Infra
White Woods
declared completion Dec 2018 · Shagun Realty
Winds Of Calm
declared completion Dec 2025 · Eiffel Lifespaces Pvt Ltd
Windsor Solitaire
possession by Dec 2027 · Silverkey Ventures LLP
Wing B Of Delta Heights
possession by Mar 2028 · Shree Hari Builders & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026