MahaRERA Property Intelligence · Mumbai City

YOGPRABHA CHSL

P51900006979 · MUMBAI · promoter Metaface India Aop

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP51900006979
Registered on17 Aug 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Metaface India Aop is the promoter of record on 2 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
YOGPRABHA1G+1830 Dec 2019

Complaints & Orders

6 complaints are on the MahaRERA record for this project, with orders passed in 6. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000020947728/12/2021Bhavin M Mehta vs M/s Metaface India AOPorder passed
CC00600000020953928/12/2021Jairaj S Khamkar vs M/s Metaface India AOPorder passed
CC00600000020960803/01/2022HIMMATLAL SHAH vs M/ METAFACE INDIA AOPorder passed
CC00600000021015322/03/2022Kamal Dhawal vs M/s Metaface India AOPorder passed
CC00600000021029723/03/2022Bharti J Ajmera vs Metaface India AOPorder passed
CC00600000021033222/03/2022Pratik N. Gandhi vs Metaface India AOPorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202231 Dec 2021a) Delay in getting MCGM approvals due to finalization of DCPR 2034 in Dec 2018 which was suppose to be issued by 2014-2016. b) Delay in clarification related to common area & RG

Location, Land & Connectivity

Located at MUMBAI, ROAD, Ward FNorth, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by LAND BEARING S NO 191 HISSA NO 02 PART, to the south by 30 FEET PUBLIC ACCESS ROAD CTS 2419A-2, to the east by 44 FEET DP ROAD S NO 191 HISSA NO02 and to the west by LAND BEARING S NO 63 HISSA NO 04 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ11 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Bhalchandra Niwas CHS
possession by Dec 2026 · Ishaan Realtors
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD

Other RERA-registered projects in Mumbai City

Zahra Residency
possession by Dec 2026 · Alliance Builders AND Developers
Zarion
declared completion Jun 2026 · AYG Homes Constructions Private Limited
ZEN 16
possession by Dec 2028 · Goodwill Infrastructure LLP
Zephyr
declared completion Jun 2025 · Aura Creators
Zeus Residency Sale Bldg No.6
declared completion Dec 2023 · Balwant Doshi
1 OSR
declared completion Mar 2023 · Shagun Builders

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026