AARYARAJ ELEGANCE

MAUJE SHIVANE · AARYARAJ DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013626

Delivery and registration

When is the project declared for completion?

AARYARAJ ELEGANCE is registered with MahaRERA as P52100013626 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013626
Registered on16 Oct 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AARYARAJ ELEGANCE record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aaryaraj Developers is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AARYARAJ ELEGANCE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
AARYARAJ ELEGANCE1G+431 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jul 2021Construction and development work is already completed. However Possession is delayed due to Lockdown caused by COVID -19 outbreak and Government Restrictions. We require time for
30 Jul 202130 Jun 2023We had completed 95% of project till now. The delay happened due to shortage of labor and material due to Pandemic. We require some additional time to complete the development wo

Location, Land & Connectivity

Located at MAUJE SHIVANE, sHIVANE VILLAGE ROAD, Haveli, Pune, 411023. Per the filed land record, the plot is bounded to the north by AMENITY SPACE, to the south by SR NO 85P, to the east by SR NO 1 and to the west by SR NO 85P. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Baner–Balewadi belt10 km
Pune Junction / city centre12 km
Hinjewadi Rajiv Gandhi IT Park15 km
Magarpatta / Hadapsar IT16 km
Kharadi / EON IT Park19 km
Pune Int'l Airport (Lohegaon)19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhugaon

Kumar Prakruti
possession by Oct 2026 · Kumar Properties Govind Shree Realtors L
Sai Orchid
possession by Oct 2026 · M/S Rudra Builders AND Developers
Aldea Annexo -C1
possession by Dec 2026 · Puranik Builders Limited
Audumbar Nest
possession by Dec 2026 · Om Chidanand Developers
Dongar Maatha
possession by Dec 2026 · M/s Starlight Projects
Sajan Siddhi D Wing
possession by Dec 2026 · Nemichand Bhandari Associates

Major developers building in Bhugaon

Other RERA-registered projects in Pune

Aashirwad
declared completion Jun 2022 · Vednirmitee Enterprises
Aashirwad Connect
declared completion Mar 2026 · Aashirwad Sucess Properties
Aashirwad Homes
possession by Dec 2026 · Nest Saswad Realty LLP
Aashish
possession by Dec 2027 · Joshi Buildcon Landmarks
Aashman Arpan
declared completion Mar 2022 · Aashman Enterprises
Aastha
possession by Dec 2028 · Resolute Buildcon LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026