AKSHAY VISTA
PIMPLE GURAV · AKSHAY SKYSCRAPERS PRIVATE LIMITED
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 May 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52100052741
Delivery and registration
When is the project declared for completion?
AKSHAY VISTA is registered with MahaRERA as P52100052741 and the promoter has declared completion for 31 May 2027.
31 May 2027
declared completion
8months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52100052741 |
| Registered on | 22 Sep 2023 |
| Promoter-declared completion | 31 May 2027 |
| Current status | Certificate Signed |
| Against today | 8 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AKSHAY VISTA record 11 quarterly progress reports since registration.
11quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Akshay Skyscrapers is the promoter of record on 22 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
22projects
registered with MahaRERA
1flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In AKSHAY VISTA, ₹11.54 Cr of a declared ₹27.01 Cr estimated project cost is reported as incurred, about 42.7%, as at the last certified filing with MahaRERA.
42.7%
₹11.54 Cr
of ₹27.01 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In AKSHAY VISTA, 11 of 56 homes filed with MahaRERA are recorded as sold or booked, about 20%, and 45 remain available.
20%sold
11 of 56 homes
₹9.58 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹3.53 Cr (about 37%) is recorded as collected and ₹6.05 Cr as receivable.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 11 registered agreements, the effective carpet rate is ₹10,670/sqft, with eight in ten falling between ₹8,310 and ₹11,345 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The inventory filing also declares: 2 not for sale.
What the filings record, home by home
Read from MahaRERA on 19 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 11 homes carry one, and 45 of the 58 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 103 | 748 sqft | Rs 73.09 lakh typical, over Rs 61.53 lakh to Rs 84.24 lakh | 4 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In AKSHAY VISTA, 25 of the 45 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 58 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A- WING | 1 | G+6 | 58 | 30 Apr 2026 |
Unit mix on the filing: 54 residential and 4 non-residential (shops/offices).
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 May 2027 | labour issue and finance constraint. |
Location, Land & Connectivity
Located at PIMPLE GURAV, KASHID PARK, , Haveli, Pune, 411061. Per the filed land record, the plot is bounded to the north by 12 METER WIDE D P ROAD, to the south by BY PART OF SURVEY NO 86, to the east by BY A PART OF SURVEY NO 87-1 and to the west by BY A PART OF SURVEY NO 87-1. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Baner–Balewadi belt | 6 km |
| Hinjewadi Rajiv Gandhi IT Park | 8 km |
| Pune Junction / city centre | 10 km |
| Pune Int'l Airport (Lohegaon) | 11 km |
| Kharadi / EON IT Park | 14 km |
| Magarpatta / Hadapsar IT | 15 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.