Pune/Project record

MahaRERA · the public record

AKSHAY VISTA

DHAYARI · OM ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

57units filed as unsoldInventory · 19 September 2026
18 Apr 2029declared completionMahaRERA registration · read 12 Jul 2026
70registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

18 Apr 2029

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100076915

Delivery and registration

When is the project declared for completion?

AKSHAY VISTA is registered with MahaRERA as P52100076915 and the promoter has declared completion for 18 Apr 2029.

18 Apr 2029

declared completion

31months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100076915
Registered on09 Jul 2024
Promoter-declared completion18 Apr 2029
Current statusCertificate Signed
Against today31 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AKSHAY VISTA record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In AKSHAY VISTA, ₹11.95 Cr of a declared ₹22.23 Cr estimated project cost is reported as incurred, about 53.8%, as at the last certified filing with MahaRERA.

53.8%

₹11.95 Cr

of ₹22.23 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In AKSHAY VISTA, 9 of 70 homes filed with MahaRERA are recorded as sold or booked, about 13%, and 61 remain available.

13%sold

9 of 70 homes

₹6.11 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹3.37 Cr (about 55%) is recorded as collected and ₹2.75 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 9 registered agreements, the effective carpet rate is ₹7,751/sqft, with eight in ten falling between ₹7,062 and ₹8,731 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 13 homes carry one, and 57 of the 70 are recorded unsold. Since we started watching this ledger, 4 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
202774 sqftRs 62.00 lakh typical, over Rs 60.00 lakh to Rs 67.59 lakh5 filed on this stack, floors 1–6

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In AKSHAY VISTA, 51 of the 57 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 56 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 70 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING A1G+835-
BUILDING B1G+835-

Unit mix on the filing: 70 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DHAYARI, NA, Haveli, Pune, 411041. Per the filed land record, the plot is bounded to the north by BY THE BOUNDRY OF VILLAGE WADGAON KH, to the south by SR NO 144 3 PROPERTY OF MR POKALE AND OTHERS, to the east by SR NO 144 1 2 PROPERTY OF MR SANAS and to the west by SR NO 144 1 3 GANESH PRASAD CHS. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Pune Junction / city centre10 km
Baner–Balewadi belt12 km
Magarpatta / Hadapsar IT14 km
Hinjewadi Rajiv Gandhi IT Park17 km
Kharadi / EON IT Park17 km
Pune Int'l Airport (Lohegaon)18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

OM Enterprises is the promoter on 10 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every OM Enterprises project & its RERA track record →

Other RERA-registered projects in Dhayari

Aqura Pride
possession by Sep 2026 · Aqura Builder And Developer Private Limi
Majestique Swapnangan Wing A And Wing B
possession by Sep 2026 · Majestique Horizon LLP
Tridal Samruddhi
possession by Sep 2026 · M/s. Tridal Associates
Vasant Vihar A Wing
possession by Sep 2026 · A R Developers
Homedale
possession by Dec 2026 · M/s. Om Shiv Sai Promoters & Develop
Navjyot Abha Phase II B And D
Not filing quarterly progress reports · possession by Dec 2026 · Sumeru Buildcon Private Limited

Major developers building in Dhayari

Other RERA-registered projects in Pune

Akshay Vrindavan
possession by Jun 2027 · Akshay Skyscrapers Private Limited
Akshay Vrindavan - A,B Building
possession by Apr 2028 · Akshay Skyscrapers Private Limited
AL Aqeeq
declared completion Dec 2019 · Centennial Realty
Alankapuram Ph 3 B And C Building
declared completion Sep 2022 · R K Lunkad Housing Corporation
Alankapuri Complex
declared completion Dec 2024 · S K Builders AND Developers
Alapshree
possession by Mar 2027 · Sonigara Ventures

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026