MahaRERA Property Intelligence · Pune

Amol Smruti

P52100025529 · Narayangaon · promoter Seema Amol Lolage

Certificate SignedDue 30 Sep 2022

Delivery & Registration

MahaRERA registrationP52100025529
Registered on28 Jun 2020
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Amol Smruti1G+531 Mar 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Narayangaon, Narayangoan Goathan, Narayangoan, Junnar, Pune, 410504. Per the filed land record, the plot is bounded to the north by Gaothan road, to the south by AdjLane, to the east by C SNO 709 and to the west by C SNO 713. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Kharadi / EON IT Park34 km
Pune Int'l Airport (Lohegaon)35 km
Magarpatta / Hadapsar IT38 km
Pune Junction / city centre42 km
Baner–Balewadi belt50 km
Hinjewadi Rajiv Gandhi IT Park52 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Narayangaon

Nirmiti Icon
possession by Aug 2026 · Nirmiti Developers
Crystal Tower
possession by Dec 2026 · Jadhav Civil Project
Divyata Park
possession by Dec 2026 · Shantaram J Gadhve
Vizion Galaxy D
possession by Dec 2026 · Vizion Construction
Landmark Paradise
possession by Jul 2027 · Landmark Promoters & Builders
Prime Vastu
possession by Jul 2027 · Prime Construction

Other RERA-registered projects in Pune

Amora
declared completion Oct 2025 · Kimaya Realities
Amora Tower
possession by Aug 2026 · Amarnath Creativity
Amorapolis A Wing
declared completion Dec 2022 · Krisna Nirmaan Skyscraper LLP
Amorapolis B Wing
declared completion Dec 2022 · Krisna Nirmaan Skyscraper LLP
Amorapolis C Wing
declared completion May 2023 · Krisna Nirmaan Skyscraper LLP
Amorapolis Phase 3
declared completion Nov 2023 · Krisna Nirmaan Skyscraper LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026