Pune/Project record

MahaRERA · the public record

Ankur City

Kasaba · ARYAN DEVELOPERS AND BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100021288

Delivery and registration

When is the project declared for completion?

Ankur City is registered with MahaRERA as P52100021288 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100021288
Registered on21 Jun 2019
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ankur City record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 23 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aryan Developers is the promoter of record on 42 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

42projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ankur City in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Block-11G+131 Dec 2023
Block-21G+131 Dec 2023
Block-31G+131 Dec 2023
Block-41G+131 Dec 2023
Block-51G+131 Dec 2023
Block-61G+131 Dec 2023
Block-71G+131 Dec 2023
Block-81G+131 Dec 2023
Block-91G+131 Dec 2023
Block-101G+131 Dec 2023
Block-111G+131 Dec 2023
Block-121G+131 Dec 2023
Block-131G+131 Dec 2023
Block-141G+131 Dec 2023
Block-151G+131 Dec 2023
Block-161G+131 Dec 2023
Block-171G+131 Dec 2023
Block-181G+131 Dec 2023
Block-191G+131 Dec 2023
Block-201G+131 Dec 2023

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Ankur City, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250297123/08/2025Mahesh Bapurao Jadhav vs ARYAN DEVELOPERS AND BUILDERSpending / no order on file

Location, Land & Connectivity

Located at Kasaba, Jamdar Road, Baramati, Pune, 413102. Per the filed land record, the plot is bounded to the north by Road, to the south by 18 Meter DP Road, to the east by Gat No 180 and to the west by Gat No 129. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~81 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Magarpatta / Hadapsar IT81 km
Kharadi / EON IT Park82 km
Pune Int'l Airport (Lohegaon)85 km
Pune Junction / city centre87 km
Baner–Balewadi belt97 km
Hinjewadi Rajiv Gandhi IT Park103 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Aryan Developers AND Builders project & its RERA track record →

Other RERA-registered projects in Baramati

Shivshri Heights
possession by Sep 2026 · Shivashri Buildcon
Adarsh Residency
possession by Oct 2026 · Shivshree Developers
Dream City -A Building
possession by Oct 2026 · Tanaji Sadashiv Pansare
Tanai Heights
possession by Nov 2026 · Surekha Vishnu Kumbhar
Tanai G
possession by Nov 2026 · Surekha Vishnu Kumbhar
Shrivishwa Heights
possession by Dec 2026 · Shrivishwa Developers

Other RERA-registered projects in Pune

Ankur Heights
possession by Jun 2028 · Not Available
Ankur Infra
possession by Mar 2028 · Ankur Infra
Ankur Residency
possession by Oct 2026 · Ankur Developers
Anmol
possession by Jun 2027 · Builtwell Constructions
Anmol Residency
declared completion Jun 2023 · Anmol Developers
Anna Awas
declared completion Oct 2024 · Muktai Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026