Pune/Project record

MahaRERA · the public record

ARISE CONSTRUCTION

BHAWANI PETH · WASIM AYUB KAMBLE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100013537

Delivery and registration

When is the project declared for completion?

ARISE CONSTRUCTION is registered with MahaRERA as P52100013537 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100013537
Registered on09 Oct 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARISE CONSTRUCTION record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Wasim Ayub Kamble is the promoter of record on 10 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARISE CONSTRUCTION in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
ARISE CONSTRUCTION1G+531 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020THERE WERE DISPUTES BETWEEN DEVELOPER AND TENANTS
30 Dec 202030 Sep 2023DUE TO FINANCIAL CRUNCH AND LOCKDOWN EVENT AND COVID 19 SITUATION

Location, Land & Connectivity

Located at BHAWANI PETH, BHAWANI PETH, Pune City, Pune, 411002. Per the filed land record, the plot is bounded to the north by CTS NO 441B-2, to the south by 24 M WIDE PROPOSED ROAD, to the east by CTS NO 455 and to the west by CTS NO 457A. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~79 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park79 km
Baner–Balewadi belt84 km
Pune Junction / city centre94 km
Pune Int'l Airport (Lohegaon)96 km
Kharadi / EON IT Park99 km
Magarpatta / Hadapsar IT100 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shukrawar Peth

Kawal Arcade
possession by Sep 2026 · Sethi Greenscape Venture
Samasta Barajati Gujarathi Mahajan
possession by Sep 2026 · Shri Samasta Barajatis Gujrati Mahajan
Dhanlaxmi Market
possession by Dec 2026 · Dhanlaxmi Infra
Aakankssha Sanskruti
possession by Dec 2026 · Aakankssha Developer
Anand
possession by Dec 2026 · Lagoo Apte Properties Private Limited
Giriraj Residency
possession by Dec 2026 · Atul Constructions

Major developers building in Shukrawar Peth

Other RERA-registered projects in Pune

Arisha
possession by Mar 2027 · Amol Ajit Ravetkar
Arisya
possession by Dec 2027 · VED Optima Reality LLP
Arkaa Galaxy
possession by Dec 2028 · Agarwal AND Bhondve Buildcon LLP
Arkaay Tower
possession by Dec 2029 · Rajwardhan Group
Arkaya Phase I
possession by Oct 2028 · High Yield Fortune Pvt Ltd
Arnav City
declared completion Mar 2023 · Sagar Babaso Choudhar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026