26units filed as unsoldInventory · 17 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52100029490

Delivery and registration

When is the project declared for completion?

ARSH COMPLAX is registered with MahaRERA as P52100029490 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52100029490
Registered on04 Jun 2021
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARSH COMPLAX record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Milan Developers is the promoter of record on 30 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

30projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARSH COMPLAX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 17 September 2026

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 1 homes carry one, and 26 of the 27 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
ARSH COMPLAX1G+631 May 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2027The project has experienced delays due to circumstances beyond our control. The progress of construction was adversely affected by force majeure conditions including disruptions ca

Location, Land & Connectivity

Located at Pune, Pune, Pune City, Pune, 411002. Per the filed land record, the plot is bounded to the north by CTS NO 814, to the south by PLOT NO 02, to the east by CTS NO 809 and to the west by CTS NO 800 AND 801. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Pune Junction / city centre3 km
Magarpatta / Hadapsar IT7 km
Kharadi / EON IT Park10 km
Baner–Balewadi belt11 km
Pune Int'l Airport (Lohegaon)11 km
Hinjewadi Rajiv Gandhi IT Park16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Milan Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Shukrawar Peth

Kawal Arcade
possession by Sep 2026 · Sethi Greenscape Venture
Samasta Barajati Gujarathi Mahajan
possession by Sep 2026 · Shri Samasta Barajatis Gujrati Mahajan
Dhanlaxmi Market
possession by Dec 2026 · Dhanlaxmi Infra
Aakankssha Sanskruti
possession by Dec 2026 · Aakankssha Developer
Anand
possession by Dec 2026 · Lagoo Apte Properties Private Limited
Giriraj Residency
possession by Dec 2026 · Atul Constructions

Major developers building in Shukrawar Peth

Other RERA-registered projects in Pune

Artmeciya
possession by Dec 2026 · M/s. Flynirvanna Builder LLP
Arun Sanctum
possession by Dec 2030 · Adev Ventures PVT LTD
Aruna Residency
declared completion Mar 2022 · Kapil Vilasrao Barge
Arunali
possession by Sep 2026 · Badhekar Properties
Arunika A,B Wing
possession by Dec 2026 · Dhareshwar Buildcon
Arunita Towers
possession by Dec 2028 · Arunita Residency LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Pune RERA red-flag register.